Exhibit A
                                                    City of Colleyville
                                                Capital Improvement Plan
                                                     Fiscal Year 2021
                                                   Project Descriptions


    Pleasant Run Road Bridge at Big Bear (White Chapel Bridge) ‐ Construction
    Program Description                                            Strategic Plan Connection
    This project will include replacement of the bridge along      3.3 Mitigate stormwater runoff and flooding risks
    Pleasant Run crossing Big Bear Creek. This project is being
    coordinated by the City of Southlake, and is being funded by
    the Federal Bridge Replacement Program (80%), State (10%),
    with the remaining portion being local (10%).


    Total Project Cost  $400,000
              Category                       Type                      Funding Source                2021
    Streets                      Bridges                     Drainage Capital Fund                  $400,000.00







    Pleasant Run Road Rehabilitation (John McCain to N City Limit)
    Program Description                                            Strategic Plan Connection
    The project includes the reconstruction of Pleasant Run Road   3.1 Upgrade the condition of major roads and
    from John McCain Road to the North City Limit. This project    neighborhood streets
    will include underground storm system, sidewalk, and ribbon
    curbs. The road work will be complete once the waterline is
    replaced.
    Total Project Cost  $1,800,000

              Category                       Type                      Funding Source                2021
    Streets                      Reconstruction              Capital Projects Fund                $1,250,000.00
    Streets                      Reconstruction              Drainage Capital Fund                  $550,000.00






    SH26 Beautification FY2021
    Program Description                                            Strategic Plan Connection
    This project is for the continuation of the median and right‐of‐  3.4 Thoroughly plan for future capital investments and
    way beautification along the SH26 corridor including the       associated costs
    gateway components of the design.

    Total Project Cost  $7,500,000
              Category                       Type                      Funding Source                2021
    Streets                      New Construction            TIF                                  $7,500,000.00