                                                    City of Colleyville
                                                Capital Improvement Plan
                                                     Fiscal Year 2021
                                                   Project Descriptions


    Streets

    Cheek‐Sparger Road (San Bar to Brown Trail) ‐ Construction

    Program Description                                            Strategic Plan Connection
    This project will provide for the reconstruction of Cheek‐     3.1 Upgrade the condition of major roads and
    Sparger Road from San Bar to Brown Trail.  The project         neighborhood streets
    includes a concrete roadway, sidewalks, curb and gutter,
    upsize existing waterline, and drainage improvements. This
    project will be funded from a grant from the North Central
    Texas Council of Governments.

    Total Project Cost  $4,105,000
              Category                       Type                      Funding Source                2021
    Streets                      Reconstruction              Capital Utility Fund                   $900,000.00
    Streets                      Reconstruction              FHA/TxDOT                            $1,877,000.00
    Streets                      Reconstruction              TIF                                  $1,328,000.00



    Flashing Lights for Pedestrian Crosswalks‐2021

    Program Description                                            Strategic Plan Connection
    This project will provide for the purchase and installation of   3.1 Upgrade the condition of major roads and
    flashing lights at pedestrian crosswalks to enhance safety.    neighborhood streets

    Total Project Cost  $75,000

              Category                       Type                      Funding Source                2021
    Streets                      School and Neighborhood Safet Capital Projects Fund                 $75,000.00






    Glade Rd (Phase 2‐SH26 to Pool) Design

    Program Description                                            Strategic Plan Connection
    Design project plans and specifications for Glade Road from    3.1 Upgrade the condition of major roads and
    SH 26 to Pool Road.                                            neighborhood streets


    Total Project Cost  $70,000
              Category                       Type                      Funding Source                2021
    Streets                      Reconstruction              TIF                                     $70,000.00