FUNDED CAPITAL IMPROVEMENT PROJECT #81



              Fiber Connectivity between Buildings (Municipal/Academy)



          Project Description:
          Improve Technology, Facilities and Equipment: Reduce critical infrastructure downtime - With the
          addition of the EOC at the new Fire/EMS station and a complete fiber duct between all of our
          locations, we have the opportunity to install our own fiber between all of the locations to provide
          faster connectivity than we can afford through vendors.  With this rollout we would start with
          10Gbps connectivity between all of our locations (approximately 100X faster than our current
          connections), with the ability to increase to 40Gbps and 100Gbps in the future. Using our own fiber
          will allow us flexibility in internet connectivity - options to combine the internet connection at each
          location into a single faster connection, or reduce or remove internet connectivity costs at one or
          more locations and route all internet traffic through a single location.  Since we have moved to a
          virtual server architecture, having our own fast fiber connectivity between locations will allow us to
          move virtual servers to any location when necessary (disaster recovery, scheduled hardware down
          time for updates, upgrades, repairs, etc.) We will be able to have our data available at any of the
          locations without any reduction in speed or productivity.
                                                       PROJECT EXPENSE
           410-74400-20-000-000081  Totals Thru  Estimated  Adopted  - - - - - - - - - - - - - - - - - Projection- - - - - - - - - - - - - - - - - -  Project
          EXPENDITURE TYPE          FY 17/18   FY 18/19  FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24   Total
          Engineering                                -               -                  -                  -                  -                  -                  -                  -
          Construction                               -               -                  -                  -                  -                  -                  -                  -
          Design                                     -               -                  -                  -                  -                  -                  -                  -
          Contingency                                -               -                  -                  -                  -                  -                  -                  -

          Other Cost                                 -         25,000          275,000                  -                  -                  -                  -          300,000
           EXPENDITURES TOTAL                        -         25,000          275,000                  -                  -                  -                  -          300,000

                                                       PROJECT FUNDING

           410-10110-20-000-000081  Totals Thru  Estimated  Adopted  - - - - - - - - - - - - - - - - - Projection- - - - - - - - - - - - - - - - - -  Project
           FUNDING TYPE             FY 17/18   FY 18/19  FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24   Total
           Cash (Fund Balance)                       -  25,000  275,000                  -                  -                  -                  -          300,000
           Bonds FY 18/19 CO                         -               -                  -                  -                  -                  -                  -                  -
           Transfer in from Utility Fund                     -               -                  -                  -                  -                  -                  -                  -
           Unfunded                                  -               -                  -                  -                  -                  -                  -                  -

           Other                                     -               -                  -                  -                  -                  -                  -                  -
           FUNDING TOTAL                             -         25,000          275,000                  -                  -                  -                  -          300,000

                                                  IMPACT ON OPERATING BUDGET

                                   Totals Thru  Estimated  Adopted  - - - - - - - - - - - - - - - - - Projection- - - - - - - - - - - - - - - - - -
           IMPACT TYPE              FY 17/18   FY 18/19  FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24
           Supplies                                  -               -                  -                  -                  -                  -                  -                  -
           Services                                  -               -                  -                  -                  -                  -                  -                  -
           Insurance                                 -               -                  -                  -                  -                  -                  -                  -
           Repair & Maintenance                      -               -                  -                  -                  -                  -                  -                  -
           Utilities                                 -               -                  -                  -                  -                  -                  -                  -
           Debt Service                              -               -                  -                  -                  -                  -                  -                  -
           OPERATING IMPACT                          -               -                  -                  -                  -                  -                  -                  -