Page 366 - City of Westlake FY20 Budget
P. 366

FUNDED CAPITAL IMPROVEMENT PROJECT #52/58


                          Ottinger Road Reconstruction/Drainage & Trail

                                                (North of Westlake Academy)

            Project Description:
            This project will provide stabilization of road subgrade and 7" asphalt to      Project 52 Trail    $     319,006
            approximately 4,000 LF of Ottinger Road (from Westlake Academy to               Project 58 R&D    $  1,063,800
            SH 170) and replace/improve culverts and ditches, consistent with 2011          Grand Total         $  1,382,806
            Graham Pavement Evaluation Study.  Anticipate crack sealing during
            the 2nd year after completion.  In conjunction with this project, the
            existing Ottinger Road bridge will be replaced with new box culvert,
            much like the Dove Road improvements.   Staff will determine through
            engineering design analysis the final design criteria including horizontal
            and vertical alignment.  A trail will provide East to West interconnectivity
            within the Westlake trail system.  Includes a primitive trail head on the
            Southeast corner of the cemetery property (primitive parking, restrooms
            and water fountain).


                                                        PROJECT EXPENSE
            410-74400-19-000-000052  Actuals Thru  Estimated  Adopted  - - - - - - - - - - - - - - - - - Projection- - - - - - - - - - - - - - - - - -  Project
            410-73000-16-000-000058   FY 17/18  FY 18/19   FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24  Total
             Trail- Engineering/Design                     -               -                  -                  -                  -                  -                  -
             Trail - Construction                     -               -                  -          319,006                  -                  -                  -          319,006
             Trail - Design                           -               -                  -                  -                  -                  -                  -

             Road/Bridge - Engineering                     -               -                  -                  -                  -                  -                  -
             Road/Bridge - Construction                     -               -                  -       1,063,800                  -                  -                  -       1,063,800
            EXPENDITURES TOTAL                        -               -                  -       1,382,806                  -                  -                  -       1,382,806

                                                         PROJECT FUNDING

            410-33501-19-000-000052  Actuals Thru  Estimated  Adopted  - - - - - - - - - - - - - - - - - Projection- - - - - - - - - - - - - - - - - -  Project
            410-33501-16-000-000058   FY 17/18  FY 18/19   FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24  Total
             Cash (Fund Balance)                      -               -                  -                  -                  -                  -                  -                  -
             Bonds FY 20/21 CO                        -               -                  -          319,006                  -                  -                  -          319,006
             Bonds FY 20/21 CO                        -               -                  -       1,063,800                  -                  -                  -       1,063,800

             Unfunded                                 -               -                  -                  -                  -                  -                  -                  -
             Other                                    -               -                  -                  -                  -                  -                  -                  -
            FUNDING TOTAL                             -               -                  -       1,382,806                  -                  -                  -       1,382,806
                            vision link  17,451,295  1,073,505  96,957  2,938,568  380,500  334,060  334,060
                                                   IMPACT ON OPERATING BUDGET

                                    Actuals Thru  Estimated  Adopted  - - - - - - - - - - - - - - - - - Projection- - - - - - - - - - - - - - - - - -
            IMPACT TYPE               FY 17/18  FY 18/19  FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24
             Supplies                                 -               -                  -                  -                  -                  -                  -                  -
             Trail - Services                         -               -                  -                  -                  -                  -                  -                  -
             Insurance                                -               -                  -                  -                  -                  -                  -                  -
             Trail - Repair & Maintenance                      -               -                  -                  -                  -                  -                  -                  -
             Trail - Rent & Utilities                      -               -                  -                  -                  -                  -                  -                  -
             Debt Service                             -               -                  -                  -            89,943            89,943            89,943                  -

            OPERATING IMPACT                          -               -                  -                  -            89,943            89,943            89,943                  -