Public Art Fund
                                                                                                                    CIP

                                                                                                       PUBLIC ART FUnD


                                   City of Southlake FY 2020 CIP Project Status Form

                                                      Public Art Program

              DEPARTMENT: Community Services Department
              PROJECT
              LOCATION:   Bob Jones Park

              PROJECT TIMELINE: 10/1/19  to  9/30/20
              DESCRIPTION:
               The purpose of this item is to establish project fund to implement the Southlake 2030
               Public Art Master Plan.










                                                                        New Request  Continuation Project  Joint Use
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
                                                                       Public Health /   Rehab or Protection      Need / Service
               Implement the Southlake 2030 Public Art Master Plan recommendations.  Safety  of Capital Stock  Enhancement
                                                                       Compliant with 2030/2035 Comprehensive Plan Element?

                                                                       List (incl ref #):
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               Delay recommendation implementation
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Quality Development
               FUND:  Public Art Fund
                                                        EXPENDITURE SCHEDULE
                   PROJECT ELEMENT  TOTAL PRIOR  2020    2021     2022     2023      2024    UNFUNDED    TOTAL
                PLANNING / FEASIBILITY STUDY                                                               0
                    ENGINEERING & DESIGN                                                                   0
                               LAND                                                                        0
                             TESTING                                                                       0
                         CONSTRUCTION                                                                      0
                              OTHER   225       100      100      100      100       100       100        825
                              TOTAL   225       100      100      100      100       100       100        825
                                                         OPERATIONAL IMPACT
                   PROJECT ELEMENT  TOTAL PRIOR  2020    2021     2022     2023      2024    UNFUNDED    TOTAL
                     MAINTENANCE COSTS                                                                     0
                      PERSONNEL COSTS                     1        1        1        1          1          5
                              TOTAL    0         0        1        1        1        1          1          5
                                                          FUNDING SCHEDULE
                   FUNDING SOURCE  TOTAL PRIOR  2020     2021     2022     2023      2024    UNFUNDED    TOTAL
                         GENERAL FUND                                                                      0
                               CCPD                                                                        0
                               CEDC                                                                        0
                HOTEL OCCUPANCY TAX FUND                                                                   0
                 PARK DEDICATION FEE FUND                                                                  0
                        PUBLIC ART FUND  225    100      100      100      100       100       100        825
                 ROADWAY IMPACT FEE FUND                                                                   0
                SANITARY SEWER IMPACT FEE                                                                  0
                               SPDC                                                                        0
                               SWUS                                                                        0
                          UTILITY FUND                                                                     0
                   WATER IMPACT FEE FUND                                                                   0
                              TOTAL   225       100      100      100      100       100       100        825
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                           SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
               CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      SWUS: STORMWATER UTILITY SYSTEM FUND
                                    Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000