Page 181 - Saginaw FY20 Annual Budget
P. 181

City of Saginaw
 Capital Improvement Plan
 2019-2023

 USE OF FUNDS                                                            SOURCE OF FUNDS
 Actual  Revised                      Tarrant     Cap Proj     General     Escrow      Donations  Enterprise   Drainage      To Be
 Project Description  Note Prior Years 2018-2019  2019-2020  2020-2021  2021-2022  2022-2023  Future CIP  Total  County  Fund  Fund  Fund  Fund  Fund  Fund  Determined
 Saginaw Blvd. System #2 Ph. 4 and Utility Relocation  7  867,685    867,685                                    867,685
 Lemon to Northern
 East Cement Creek Improvements  8  324,398    324,398  65,080                                                  259,318
 Culvert at Opal Street
 Saginaw Blvd. System # 2 Ph. 6  1,600,000  1,600,000                                                                        1,600,000
 Northern to Cambridge
 Saginaw Blvd. System # 2 Ph. 7  675,000  675,000                                                                             675,000
 Cambridge to Across from Minton
 East Cement Creek Improvements Phase 2  165,100  1,240,000  0  0  1,405,100                                  1,405,100              0
 Channel improvement Opal to Blueridge&Blueridge drainage
 East Cement Creek Improvements Phase 3  164,000  1,759,000  0  0  1,923,000                                  1,923,000              0
 Channel to McLeroy (Blue Ridge St. Internal Drainage)
 Meadow Street Ditch Improvements  675,000  675,000                                                                           675,000
 1,500 LF channel behind homes on Meadow Dr
 Saginaw Blvd. System #3 Right of Way  9  530,000  530,000                                                                    530,000
 Easements, RR Permits, RR Inspection
 Saginaw Blvd. System #3 Ph. 1  2,500,000  2,500,000                                                                         2,500,000
 Saginaw Blvd. System #3 Ph. 2  1,500,000  1,500,000                                                                         1,500,000
 Saginaw Blvd. System #3 Ph. 3  310,000  310,000                                                                              310,000
 Saginaw Blvd. System #3 Ph. 4  1,100,000  1,100,000                                                                         1,100,000
 Saginaw Blvd. System #3 TXDOT Review  10  750,000  750,000                                                                   750,000
 Total Drainage System  1,192,082  165,100  1,404,000  1,759,000  0  0  9,640,000  14,160,182  0  65,080  0  0  0  0 4,455,103  9,640,000

 Total Capital Projects  28,431,457  4,184,755 13,403,050  6,010,000  373,600  171,000 144,296,000 196,869,862 7,164,986 30,057,699  919,608 3,470,078  110,000 7,336,390 4,723,103 143,088,000


 Notes
 1 Project funded through cash reserves
 2 Includes two (2) grant applications to Texas Parks and Wildlife Department
 3 Project funded through Utility Impact Fees
 4 Projects constructed by City of Fort Worth
 5 Projects possible constructed by Developers
 6 Utility Relocation Project for TXDOT Highway Expansion
 7 Paid with Drainage Utility Reserves
 8 Paid with Cap Proj Reserves and Drainage Utility Fund
 9 Paid with Drainage Utility Fees
 10 On hold due to TXDOT Review Fee Issue