Page 40 - NRH FY20 Approved Capital Budget
P. 40

TOTAL  782,400  294,000  689,275  300,000  380,000  380,000  300,000  151,200  217,000  79,864,580  121,538,119  88,466,205  20,089,927  12,301,987  680,000  121,538,119
                                                                                                                                                                     $       $                                              $





                                    FY 2025/26  782,400                294,000                -                       -                       -                       -                       -                       -                       -                       25,717,070  $       25,717,070  $       24,667,070           -                       1,050,000             -                       25,717,070  $









                                    FY 2024/25  -                       -                       -                       300,000                -                       -                       -                       -                       -                       13,457,480  $       13,457,480  $       12,407,480           -                       1,050,000             -                       13,457,480  $








                                    FY 2023/24  -                       -                       -                       -                       -                       -                       -                       -                       217,000                11,733,000  $       11,733,000  $       10,683,000           -                       1,050,000             -                       11,733,000  $









                                    FY 2022/23  -                       -                       -                       -                       -                       -                       300,000                -                       -                       10,891,600  $       11,066,600  $       10,016,600           -                       1,050,000             -                       11,066,600  $








                                    FY 2021/22  -                       -                       689,275                -                       380,000                380,000                -                       151,200                -                       8,773,255  $         8,773,255  $         7,723,255             -                       1,050,000             -                       8,773,255  $







             FISCAL YEAR 2019-2020 STREETS & SIDEWALK CAPITAL BUDGET  LONG RANGE PLAN FY 2019 THROUGH 2026  FY 2020/21  -                       -                       -                       -                       -                       -                       -                       -                       -                       6,878,800  $         6,878,800  $         5,828,800             -                       1,050,000             -                       6,878,800  $         37











                               ADOPTED  BUDGET  FY 2019/20  -                       -                       -                       -                       -                       -                       -                       -                       -                       2,413,375  $         2,413,375  $         380,000                -                       2,033,375             -                       2,413,375  $








                                                                 -
                                  PROJECT  TO DATE                                                                                                                                                                                  $                        41,498,539  $       16,760,000           20,089,927           3,968,612             680,000                41,498,539  $
                                                    -
                                                 -
                                                      -
                                                           -
                                                         -
                                               -
                                       -
                                         -
                                            -










                                    PROJECT NAME Traffic Signal Infrastructure Upgrades - Internal Components Traffic Signalization at Davis Boulevard & Creek View Drive Traffic Signalization at Mid-Cities Boulevard / Ice House Drive / M                     Traffic Signalization at Rufe Snow & Browning Drive Walker Boulevard and Boulevard 26 Signalization Infrastructure
                                       Timberidge Drive Street Improvements Timberline Court Street Improvements  Willowcrest Court North Street Improvements Woodbend Park Street Improvements  Total New Projects  Total Project Costs  Funding  Sources  Debt Issuance  Federal/State Grants  Total Funding Sources




















                                    PROJECT #                                           Reserves  Other
   35   36   37   38   39   40   41   42   43   44   45