FISCAL YEAR 2019-2020 STREETS & SIDEWALK CAPITAL BUDGET  LONG RANGE PLAN FY 2019 THROUGH 2026  TOTAL FY 2025/26 FY 2024/25 FY 2023/24 FY 2022/23 FY 2021/22 FY 2020/21  782,400                782,400                -                       -                       -                       -                       -                       294,000                294,000                -                       -                       -                       -                       -                       689,275                -                       -                       -                       -



                               ADOPTED  BUDGET  FY 2019/20  -                       -                       -                       -                       -                       -                       -                       -                       -                       2,413,375  $         2,413,375  $         380,000                -                       2,033,375             -                       2,413,375  $







                                                                 -
                                  PROJECT  TO DATE                                                                                                                                                                                  $                        41,498,539  $       16,760,000           20,089,927           3,968,612             680,000                41,498,539  $
                                                    -
                                                 -
                                                      -
                                                           -
                                                         -
                                               -
                                       -
                                         -
                                            -










                                    PROJECT NAME Traffic Signal Infrastructure Upgrades - Internal Components Traffic Signalization at Davis Boulevard & Creek View Drive Traffic Signalization at Mid-Cities Boulevard / Ice House Drive / M                     Traffic Signalization at Rufe Snow & Browning Drive Walker Boulevard and Boulevard 26 Signalization Infrastructure
                                       Timberidge Drive Street Improvements Timberline Court Street Improvements  Willowcrest Court North Street Improvements Woodbend Park Street Improvements  Total New Projects  Total Project Costs  Funding  Sources  Debt Issuance  Federal/State Grants  Total Funding Sources





















                                    PROJECT #                                           Reserves  Other