Page 195 - NRH FY20 Approved Capital Budget
P. 195

Parks & Recreation Capital Projects
        Department                                             Project Title                         Project Number
        Parks and Recreation                        Park Infrastructure Maintenance 2018                  PK1804
        Project Description
        This project provides for maintenance of park infrastructure in response to use and age. The FY 2017-2018 priorities include
        concrete trail repair, retaining wall repairs, park restroom partitions and fixtures, athletic field fencing, erosion control, playground fall
        zone material, security lighting maintenance, restroom/concession building repairs and drinking fountain repairs and replacement.







        Project Justification
        The Parks and Recreation Department developed an Infrastructure Management Plan for park amenities. The plan addressed long
        term funding needs for replacement and renovation of park sites and their amenities, demonstrating responsible stewardship of
        property assets by the city. Park assets are subject to continual heavy usage by citizens, exposure to the elements and the natural
        aging process. The Asset Management Plan and ongoing park inspections are used to identify assets that have become worn,
        unsafe or unsightly and to create a priority timeline for their repair, renovation or removal.


        Note: Project funding source is Park Sales Tax.










        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2017-18       $292,400
        Engineering/Design                                Revision          2017-18         $9,505
        Land/ROW Acquisition                              Total                           $301,905
        Construction               10/2017      01/2020
        Other
        Total Schedule             10/2017      01/2020
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves
        Sales Tax                     301,905           0             0             0      $301,905
        Other
        Total Funding                $301,905          $0            $0            $0      $301,905
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                  301,905           0             0             0      $301,905
        Other
        Total Costs                  $301,905          $0            $0            $0      $301,905
        Operating Impact
        There is no operating impact as a result of this project.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             181