Page 191 - NRH FY20 Approved Capital Budget
P. 191
Parks & Recreation Capital Projects
Department Project Title Project Number
Parks and Recreation Northfield Park Renovation PK1603
Project Description
This project involves the redevelopment of the existing community park through the design and construction of new amenities based
on meetings to gather stakeholder input. Recommended park elements for the redevelopment of the park include a new park entry, a
more efficient park layout, upgrade of all equipment and support facilities and introduction of loop trails. The project will also ensure
the protection of the natural creek corridor and provide engaging views to natural areas.
Project Justification
The Northfield Park Redevelopment Project was the top recommendation under the Renovation and Improvement category of the
2007 Park, Recreation and Open Space Master Plan. The 29 acre park is one of the original four parks developed in the City, and
the amenities are aged and in need of removal or renovation. The redevelopment project will provide the opportunity to correct many
issues while emphasizing positive aspects of the park site. The adjacent 17 acre natural area immediately east of the park was
donated to the City as required by the Little Bear Creek Ordinance, and as a result of the Thornbridge Development. In September of
2014, a connection of the John Barfield Trail was constructed in the once untouched natural area and meanders westward into the
original Northfield Park. This new bicycle/pedestrian connection is a vital link to Northfield Park from all Thornbridge neighborhoods,
Grace Meadows neighborhoods and to the Cotton Belt Trail and to the City of Hurst to the east and to Forest Glenn and the City of
Keller. This project will provide an investment in one of the city's established residential areas, improving the delivery of parks and
recreation services allowing continued reinvestment in our City.
Note: Funding source Certificates of Obligation ($3,900,000), Federal/State Grants ($500,000), Reserves Category includes Sales
Tax Reserves ($100,536) and Project Savings ($127,485 Trail Head Gateways 2015) and $33,138 from PK9601, Sales Tax
($405,500), and Other Category includes Impact Fees ($900,000) and Barfield Family Private Foundation ($150,000).
Project Schedule Beginning Date Ending Date History Fiscal Year Amount
Professional Services Adopted Budget 2015-16 $3,697,000
Engineering/Design 03/2016 08/2017 Adopted Budget 2016-17 $603,000
Land/ROW Acquisition Revision 2016-17 $5,500
Construction 11/2017 11/2018 Revision 2017-18 $33,138
Other Revision 2018-19 $8,653
Total Schedule 03/2016 11/2018 Total $6,125,312
Sources of Funds To Date 2019-20 Budget 2020-21 Estimate 2021-Completion Total Funding
General Obligation Bonds
Certificates of Obligation 3,900,000 0 0 0 $3,900,000
Federal/State Grants 500,000 0 0 0 $500,000
Reserves 269,812 0 0 0 $269,812
Sales Tax 405,500 0 0 0 $405,500
Other 1,050,000 0 0 0 $1,050,000
Total Funding $6,125,312 $0 $0 $0 $6,125,312
Project Costs To Date 2019-20 Budget 2020-21 Estimate 2021-Completion Total Cost
Professional Services
Engineering/Design 419,932 0 0 0 $419,932
Land/ROW Acquisition
Construction 5,705,380 0 0 0 $5,705,380
Other
Total Costs $6,125,312 $0 $0 $0 $6,125,312
Operating Impact
No operating impact is anticipated.
Fiscal Year 2019-20 2020-21 2021-22 2022-23 2023-24 Total Impact
Amount $0 $0 $0 $0 $0 $0
Total Operating Impact $0 $0 $0 $0 $0 $0
177