Page 125 - NRH FY20 Approved Capital Budget
P. 125

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                             College Hill Ground Storage Tank Stand Pipe              UT1701
        Project Description
        This project will consist of constructing two water pipes so the storage tank will fill from the top.  The pipe being added is called a
        stand pipe.  This will allow new water to be added to the tank in order to mix with the older water in the tank.









        Project Justification
        Currently water enters the tank at the bottom of the tank. The fresh water pushes the existing older water up to the top of the tank.
        As the tank empties, the fresh water at the bottom of the tank gets pumped out in to the system. The installation of the stand pipe
        will allow the fresh water to mix with the existing water when it enters the tank, keeping the water quality at acceptable levels.


        Funding source: Utility Operations for Capital Projects.












        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2016-17        $85,000
        Engineering/Design                                Total                            $85,000
        Land/ROW Acquisition
        Construction               10/2016      09/2019
        Other
        Total Schedule             10/2016      09/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        R  e  s  e  r  v  e  s        8  5  ,  0  0  0  0             0             0       $85,000
        Sales Tax
        Other
        Total Funding                 $85,000          $0            $0            $0       $85,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                  85,000            0             0             0       $85,000
        Other
        Total Costs                   $85,000          $0            $0            $0       $85,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0