Page 291 - Mansfieldr FY20 Approved Budget
P. 291

Multi-Year Summary
                                                    Utility Construction

                                                   Budget     Budget     Budget   Budget    Budget
                Utility Construction              2019-2020  2020-2021  2021-2022  2022-2023  2023-2024  Total
                Staffing allocation                                506,130                   521,314              536,953              553,062              569,654 $        2,687,113
                Prior Year Projects                             1,239,452                           $        1,239,452
                Hogpen Branch Channel Stabilization                       1,000,000                 $        1,000,000
                Design-Final Expansion of Water Treatment Plant                 1,000,000           $        1,000,000
                Mansfield International Business Park                  2,000,000                    $        2,000,000
                Misc Utilities Roadway Projects                     600,000                   600,000              600,000              600,000              600,000 $        3,000,000
                S.H. 360 Lift Station Construction                  1,000,000                       $        1,000,000
                36" Upper Pressure Plain Water Line                  1,500,000                      $        1,500,000
                Clearwell #4 Water Treatment Plant                  9,096,000                       $        9,096,000
                Southwest Elevated Water Tower                  5,128,426                           $        5,128,426
                12/16" Water Line-SH 360                                                  1,134,300  $        1,134,300
                16" Water Line-SH 360                                                     1,879,800  $        1,879,800
                12" Sewer Main-North US HWY 287                                 2,676,700           $        2,676,700
                16" Water Line- FM 917                                          1,533,500           $        1,533,500
                GAC Filters 1-8                                                 1,200,000           $        1,200,000
                12/16" Water Line-HWY 287                                                 1,536,700  $        1,536,700
                12" Water Line-HWY 287                                                       665,100  $           665,100
                Land Acquisition                                                             692,200  $           692,200
                Final Expansion-Bud Ervin Treatment Plant                                         21,630,000 $      21,630,000
                WTP High Service Pump Station Expansion                                             4,983,600 $        4,983,600
                16/24" Water Line Walnut Creek                            1,951,500                 $        1,951,500
                12/15" Sewer Main Walnut Creek Upper Basin                3,241,500                 $        3,241,500
                24" Water Line Newt Patterson                             1,200,000                 $        1,200,000
                Total                           $            21,070,008 $            8,514,314 $       7,547,153 $        7,061,162 $      27,783,254 $      71,975,891

                Utility Construction             Budget      Budget    Budget    Budget    Budget
                Operational Cost                2019-2020   2020-2021  2021-2022  2022-2023  2023-2024  Total
                 Utilities                           19,854    100,450   103,463   106,567   109,764   440,098
                 Staffing                            63,799     65,713    67,684    69,715    71,806   338,718
                 Operations & Maintenance            33,600     84,608    87,146    89,761    92,453   387,568
                Total                         $                  117,253 $               250,771 $          258,294 $           266,043 $           274,024 $        1,166,384

               Funding for projects in FY 2019-2020 will come from impact fees and cash on hand. No debt will be
               issued in FY 2019-2020. The funding for utility improvements in future years will be evaluated annually
               to determine the amount of debt needed to be issued as population growth continues along the southeast
               and southwest corridors along Highway 360 and Highway 287.


                                 Beginning in FY 2019-2020, Utility infrastructure projects include:

               $5,128,426- Southwest Elevated Water Tower
               Construction of a 2,000,000 gallon storage tank is planned in FY 2019-2020 on the MEDC property at
                               th
               Easy Drive and 6  Avenue.

               $1,000,000- Highway 360 Lift Station
               Design and replacement of the existing lift station on State Highway 360.

               $9,096,000- Clearwell Construction
               Clearwell #4 will add additional capacity to the Water Treatment Plant’s storage capabilities.





                                                                                                         291