                             Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
                                        Objective 1: Plan and Implement Stormwater Projects
                       Project                     Performance Measure(s)           City Service Team (Department)
             Core   Stormwater Projects    Implement projects that mitigate flooding   Economic Development and
             PS                          concerns                                  Capital Investment (PWT)
             2.1.1
             Summary:

             Stormwater Projects are funded through the
             Stormwater Utility Fee and are included in the annual
             capital budget. The projects listed below are
             expected to begin or complete construction during
             FY 2019. Project milestones listed in the table will be
             updated as they occur during the year.

             Update:
             The construction contracts for the Washington
             Erosion and Matthews Court Phase 1 Drainage
             Improvement projects were advertised for bidding.
             Contract award is anticipated in the first quarter of
             FY 2020.

             Matthews Court Phase 2 Drainage Improvements
             projects are in the easement acquisition phase.

             Bidding of the Kee Branch Trib 4 has been delayed
                                                                        Completed JC‐9 Erosion Project
             due to the need for an additional public meeting to

             address citizen concerns. The project is now
             proceeding with final design and easement
             acquisition.                                    Country Club Channel and Drainage improvements are

                                                           underway.
             The Kee Branch Trib 1 Erosion Project design will not
             proceed under the original contract. Improvements
             will be made to existing infrastructure in the stream   The estimated completion date for the Sublett Creek
             under a separate design contract.             Neighborhood Improvements has been corrected from
                                                           November 2018 to 2019 in the table below.

                     Stormwater Capital Improvement Project      Estimated   Actual Bid   Estimate    Actual
                                                                 Bid Dates    Dates     Completion   Completion
              Sublett Creek Neighborhood Drainage Improvements   Apr. 2018   Nov. 2018   Nov. 2018
              Greencove Drainage Improvements                  Apr. 2018    Apr. 2018   Feb. 2019   May 2019
              JC‐9 Erosion Repair                              May 2018     July 2018   Nov. 2018   Nov. 2018
              Washington Erosion Project                       Sept. 2018
              Country Club Drainage Improvements               Sept. 2018   June 2019   Apr. 2020
              Matthews Court Drainage Improvements Phase 1     Dec. 2018
              Matthews Court Drainage Improvements Phase 2     June 2019
              Kee Branch Trib 4 Erosion                        June 2019
              Kee Branch Trib 1 Erosion                        Aug. 2019
              Harvest Hills Drainage Improvements Phase 1      Aug. 2019





                                                             129