Page 320 - Ord 866 Adopting a revised Fiscal Year 17-18 and new proposed Fiscal Year 18-19 budget
P. 320

CAPITAL PROJECT FORECAST
                Formerly Adopted and New Proposed Projects


                                                            Totals     FY 17- 18   FY 18- 19   FY 19- 20   PROJECT
            Dept  Proj     Project Description               thru      Estimated   Proposed   Projected    GRAND
            No.  No.                                       FY 16/ 17   Budget      Budget      Budget       TOTAL
          FUND 405 -  MUNICIPAL FACILITIES
             X   405  Fire Station Complex                   2,737,121$           7,339,673$           2,399,630$         -$                    12,476,424$
                TOTAL FUND 405                               2,737,121  7,339,673   2,399,630          -                      12,476,424

          FUND 412 -  ACADEMY FACILITIES
             X   412  Academy Expansion ( Master Plan Update)-                      -                        85,000                -                      85,000
                TOTAL FUND 412 -                     -                                85,000               -                      85,000

          FUND 410 -  CAPITAL PROJECTS
             16  CP20  FM1938 Town Improvements              3,035,361    50,000     220,000              -                      3,305,361
             16  CP34  Roanoke Road Reconstruction &  Drainage South  2,900                  -                      -                        480,180  483,080
             16  CP40  Sam School Road Reconstruction &  Drainage -                      -                        281,960              -                      281,960
                     FM 1938 &  Dove Road Traffic Signal (Cash)  277,730  160,000              -                      -
             16  CP68                                                                                         464,119
                     FM 1938 &  Dove Road Traffic Signal (Contribution)  26,389 -                      -                      -
             16  CP70  FM 1938 and Solana Traffic Signalization  294,703  10,000                -                      -                      304,703
             16  CP75  Flashing Crosswalk -  Dove/ Pearson &  Dove/ Ottinger -                      -                        80,000                -                      80,000
             16  CP78  Solana Pavement Repairs -                      -                        90,000                -                      90,000
             16  CP79  Wyck Hill Pavement Resurface -                      -                        54,450                -                      54,450
             16  CP80  FM1938 Pavement Repairs -                      -                        80,000                -                      80,000
                Sub-Total -  Road/ Street Improvements       3,637,083   220,000     806,410     480,180     5,143,673
             17  CP71  WA Outdoor Learning Space              129,808     175,000              -                        123,595  428,403
             17  CP77  WA Pond Repairs -                      -                        82,000                -                      82,000
                Sub-Total -  Academic Facilities Improvements  129,808   175,000      82,000     123,595      510,403

             19  CP42  Trail Connection at Hwy 114 & Solana Blvd.-                      -                        30,000                -                      30,000
             19  CP67  Wayfinding Signage -                      -                        229,500              -                      229,500
             19  CP76  Cemetary Improvements -                            100,000     50,000                -                      150,000
                Sub-Total -  Trail/ Park/ Cemetery Improvements -                       100,000  309,500             -                      409,500
             19  CP52  Trail -  Academy to Cemetery -                      -                      -                        300,949
                                                                                                             1,284,903
             16  CP58  Ottinger Road Recon/ Drainage -                      -                      -                        983,954
             19  CP53  Trail -  Dove/ Pearson/ Aspen -                      -                        290,016              -
                                                                                                              694,141
             16  CP60  Pearson Lane Recon/ Drainage -                      -                        404,125              -
                Sub-Total -  Trail and Road Improvements -                     -                       694,141  1,284,903  1,979,044
             20  CP81  Firber Connectivity Project -                      -                        300,000              -                      300,000
                Sub-Total -  Information Technology Improvements -                     -                       300,000             -                      300,000
                TOTAL FUND 410                               3,766,891   495,000    2,192,051   1,888,678    8,342,620

                                   TOTAL GOVERNMENTAL PROJECTS  6,504,012$          7,834,673$        # $         4,676,681 #  1,888,678$       #  20,904,044$


                                                            Totals     FY 17-18    FY 18-19    FY 19-20    PROJECT
                           Funding Summary                   thru      Estimated   Proposed   Projected    GRAND
                                                           FY 16/ 17   Budget      Budget      Budget       TOTAL
                     Contributions ( Formerly adopted)        321,092$              110,000$              50,000$              -$                    481,092$
                     Foundation Contribution                  129,808     175,000        0       123,595      428,403
                     TOTAL CONTRIBUTIONS                      450,900    285,000      50,000     123,595      909,495

                      Cash/ Fund Balance ( Formerly adopted)  3,315,991   210,000    605,000         0       4,130,991
                     TOTAL CASH                              3,315,991   210,000     605,000         0       4,130,991

                      FY 17/ 18 Fire Station - 20 yr Bonds   2,737,121   7,339,673  2,399,630        0      12,476,424
                      FY 18/ 19 Street/ Trail -  20 yr Bonds     0           0      1,622,051   1,765,083    3,387,134
                     TOTAL BONDS                             2,737,121  7,339,673   4,021,681   1,765,083   15,863,558
                                      GRAND TOTAL ALL PROJECTS  6,504,012$          7,834,673$         $        4,676,681  1,888,678$         20,904,044$