Page 75 - Mansfield 2019 Operating Budget
P. 75

Summary of Utility Construction Projects


                   Note: costs include the expected collection of impact fees and may vary from amounts
                   borrowed depending upon the anticipated collection of impact fees.

                   FY 2019 - $12,056,633

                       •  12” Water Line North Main Street
                       •  Hwy 360 Lift Station Rehab Design
                       •  Clearwell Construction Administration and 36” Design
                       •  Clearwell #4 @ Bud Ervin Water Treatment Plant-Construction
                       •  Misc. Utilities for Roadway Bond Projects

                   FY 2020 - $3,500,000

                       •  Hwy 360 Lift Station Construction
                       •  12” Water Line North Main Street
                       •  Final Expansion of Bud Ervin Water Treatment Plant (60MGD) - APAI
                       •  Misc. Utilities for Roadway Bond Projects

                   FY 2021 - $2,100,000

                       •  24” Water Line Newt Patterson
                       •  Reassess Walnut Creek Interceptor
                       •  Misc. Utilities for Roadway Bond Projects

                   FY 2022 - $17,750,000

                       •  Final Expansion of Bud Ervin Water Treatment Plant (60MGD)
                       •  Lone Star 2.5 MG EST
                       •  Misc. Utilities for Roadway Bond Projects

                   FY 2023 - $950,000

                       •  Water and Wastewater CIP, Impact Fee Study
                       •  Misc. Utilities for Roadway Bond Projects

                   FY 2024 - $600,000

                       •  Misc. Utilities for Roadway Bond Projects