Page 220 - Colleyville FY19 Budget
P. 220

City of Colleyville                               Capital Improvement Program



      Water Project 8: Install Pressure Relief and Flow Control Valves to                  Funding Year
      Regulate Flow Between High and Low Pressure Planes                                              2019


      Program Description
      The project includes the addition of two pressure release and flow control valves to regulate flow from the northeast section
      of the high pressure plane into the northwest portion of the low pressure plane. The project also includes associated vaults
      and connecting 8” and 12” piping.  Project costs include the rehabilitation of John McCain from Monticello Parkway west
      330'.






      Total Project Cost                    O and M Annual Costs               Project Start Date   Project End Date
                    $348,000                              $0.00                       TBD                  TBD
      Funding

      Capital Projects Fund                               $0    Perimeter Street Fees                               $0
      CEDC (Parks, Trails & Libraries)                    $0    TIF                                                 $0
      County Funding                                      $0    Tomorrow Fund ‐ Colleyville                         $0
      Crime Control and Prevention Dis                    $0    Tomorrow Fund ‐ Parks                               $0

      Drainage Fund                                       $0    Capital Utility Fund                          $348,000
      FHA/TxDOT                                           $0    Wastewater Impact Fees                              $0
      General Fund                                        $0    Water Impact Fees                                   $0
      Impact Fees ‐ Area I (East of 26)                   $0    Other:  City Funding                                $0
      Impact Fees ‐ Area II (West of 26)                  $0    Other:  Non‐City Funding                            $0

      Parkland Dedication Fund                            $0    Total Funding                                $348,000
                                                                Non Funded                                          $0




     Business Plan Connection
       The Water and Wastewater Master Plan was updated in FY 2014 and
       identifies needed capital projects through the year 2034; continue execution
       of the 27 capital projects identified in the 2014 Water and Wastewater
       Master Plan.






     Strategy Map Connection
       3.2 Ensure regular repair and replacement of water and wastewater facilities








                                                                                                         215