      Water Project 10:  Apple Valley Subdivision/Rustic Oaks                              Funding Year
      Subdivisions/ Bills Lane Water Lines ‐ DESIGN                                                   2019


      Program Description
      The project includes the addition of an 8” PVC line to connect Apple Valley Drive to Bills Lane, and replacement of a 2‐inch
      pipeline along Black Drive with an 8‐inch pipe. This project addresses looping issues of the pipeline in that area and
      bottleneck concerns of the existing 2‐inch pipe.  Individual dead‐end pipelines exist on Apple Valley Drive and Bills Lane, and
      existing 2‐inch bottleneck on Black Drive. These connector pipes will address those dead ends, provide increased fire flow to
      the residences in that area, and remove a known bottleneck.





      Total Project Cost                    O and M Annual Costs               Project Start Date   Project End Date
                    $70,000                               $0.00
      Funding

      Capital Projects Fund                               $0    Perimeter Street Fees                               $0
      CEDC (Parks, Trails & Libraries)                    $0    TIF                                                 $0
      County Funding                                      $0    Tomorrow Fund ‐ Colleyville                         $0
      Crime Control and Prevention Dis                    $0    Tomorrow Fund ‐ Parks                               $0

      Drainage Fund                                       $0    Capital Utility Fund                           $70,000
      FHA/TxDOT                                           $0    Wastewater Impact Fees                              $0
      General Fund                                        $0    Water Impact Fees                                   $0
      Impact Fees ‐ Area I (East of 26)                   $0    Other:  City Funding                                $0
      Impact Fees ‐ Area II (West of 26)                  $0    Other:  Non‐City Funding                            $0

      Parkland Dedication Fund                            $0    Total Funding                                  $70,000
                                                                Non Funded                                          $0




     Business Plan Connection
       The Water and Wastewater Master Plan was updated in FY 2014 and
       identifies needed capital projects through the year 2034; continue execution
       of the 27 capital projects identified in the 2014 Water and Wastewater
       Master Plan.






     Strategy Map Connection
       F2 ‐ Invest to provide and maintain high quality public assets