City of Colleyville                               Capital Improvement Program



      City Hall/Library ‐ HVAC Replacement                                                 Funding Year
                                                                                                      2019


      Program Description
      This project will replace the air‐conditioning units at the City Hall/Library.  These units were installed in 2002 and the typical
      life cycle for these units is 15 years.  This project is recommended for 2019 based on life‐cycle planning.










      Total Project Cost                    O and M Annual Costs               Project Start Date   Project End Date
                    $327,600                              $0.00                       TBD                  TBD
      Funding

      Capital Projects Fund                               $0    Perimeter Street Fees                               $0
      CEDC (Parks, Trails & Libraries)                    $0    TIF                                           $327,600
      County Funding                                      $0    Tomorrow Fund ‐ Colleyville                         $0
      Crime Control and Prevention Dis                    $0    Tomorrow Fund ‐ Parks                               $0

      Drainage Fund                                       $0    Capital Utility Fund                                $0
      FHA/TxDOT                                           $0    Wastewater Impact Fees                              $0
      General Fund                                        $0    Water Impact Fees                                   $0
      Impact Fees ‐ Area I (East of 26)                   $0    Other:  City Funding                                $0
      Impact Fees ‐ Area II (West of 26)                  $0    Other:  Non‐City Funding                            $0

      Parkland Dedication Fund                            $0    Total Funding                                $327,600
                                                                Non Funded                                          $0




     Business Plan Connection
       A ten‐year building component replacement program has been developed.
       Make improvements to aging facilities.  Identify funding for the building

       component replacement needs. Make improvements to aging facili es.







     Strategy Map Connection
       3.4 Thoroughly plan for future capital investments and associated costs