FIVE‐YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) IMPACT ON OPERATING BUDGET

                                         FY 2017‐18 &
            Fiscal Year                               FY 2018‐19  FY 2019‐20   FY 2020‐21  FY 2021‐22  FY 2022‐23
                                            Prior
                                                    STREET SYSTEM PROJECTS

                                                        ACTIVE PROJECTS
            FM 1709 and Keller Smithfield Road   The project is related to improvements of an existing intersection.  Minimal operating impact is anticipated, and can be
            Intersection              absorbed within the current street maintenance budget.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
            FM 1709 and Rufe Snow Drive   The project is related to improvements of an existing intersection.  Minimal operating impact is anticipated, and can be
            Intersection              absorbed within the current street maintenance budget.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The project is related to improvements of an existing roadway and is maintained by TxDOT.  Minimal operating impact is
            FM 1938 Ext.
                                      anticipated, and can be absorbed within the current street maintenance budget.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The project relates to the annual capital maintenance of city sidewalks which is funded thru the operating budget funds.
            2016 Sidewalk Construction
                                      Annual maintenance should reduce long‐term costs by avoiding full repairs and/or replacements.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The project is related to improvements of an existing roadway.  Minimal operating impact is anticipated, and can be
            Wall Price‐Keller Road Improvements
                                      absorbed within the current street maintenance budget.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
            Keller Hicks Quiet Zone / Road Widening  The project is related to improvements of an existing roadway.  Minimal operating impact is anticipated, and can be
            Project                   absorbed within the current street maintenance budget.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The project has annual impact related to maintenance and upkeep of the area which was included in the FY 2017‐18
            Old Town Keller
                                      budget.
            Grounds Maintenance         $                  77,000 $                  77,000 $                  77,000 $                  77,000 $                  77,000 $                  77,000
            Total                       $                  77,000 $                  77,000 $                  77,000 $                  77,000 $                  77,000 $                  77,000

            Mt. Gilead and US 377 Intersection   The project is related to improvements of an existing intersection.  Minimal operating impact is anticipated, and can be
            Improvements              absorbed within the current street maintenance budget.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐

                                      The project relates to the annual capital maintenance of city streets which is funded thru the operating budget funds.
            2016 Street Reconstruction Project
                                      Annual maintenance should reduce long‐term costs by avoiding full repairs and/or replacements.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The project relates to the annual capital maintenance of city streets which is funded thru the operating budget funds.
            2017 Street Reconstruction Project
                                      Annual maintenance should reduce long‐term costs by avoiding full repairs and/or replacements.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The scope of the project has yet to be determined, however, it would be replacement of a current tunnel system.
            Old Town Keller Tunnel
                                      Minimal operating impact is anticipated, and can be absorbed within the current street maintenance budget.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The project relates to the annual capital maintenance of city sidewalks which is funded thru the operating budget funds.
            2017 Sidewalk Construction
                                      Annual maintenance should reduce long‐term costs by avoiding full repairs and/or replacements.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐
                                      The project relates to the annual capital maintenance of city streets which is funded thru the operating budget funds.
            2018 Street Reconstruction Project
                                      Annual maintenance should reduce long‐term costs by avoiding full repairs and/or replacements.
            Total                       $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐ $                             ‐