FY2030 Street Improvement Project                                         PROJECT #


         PROGRAM: STREETS PROJECT                             PROJECT MANAGER:              MATT COX


         DESCRIPTION                                            JUSTIFICATION
         1. Roaring Creek Ct, $420,000                          Based on the 2022 Trophy Club Streets/Pavement Study and using
         Concrete Street Replacement of Roaring Cree Ct, from Creek Courts  the Pavement Condition Index (PCI), Structural Strength Index
         Dr to end of Roaring Creet Ct, approvimately 6,500 sq ft.  (SSI), and Overall Condition Index (OCI) ratings.
         2. Oak Village Ct & Ln, $790,000
         Concrete Street Replacement of Oak Village Ct & Ln, approximately  1.Roaring Creek Ct- PCI 34, SSI 82.83, OCI 34
         18,000 sq ft.
         3. Timberline Dr, $1,550,000                           2.Oak Village Ct & Ln- PCI 55, SSI 91.49, OCI 65
         Concrete Street Replacement of Timberline Dr. from Indian Creek
         and 1 Timberline Dr to 39 Timberline Dr and Greenleaf Dr,  3.Timberline- PCI 36, SSI 100, OCI 46
         approximately 34,000 sqft.





         FUNDING TIMELINE

         2026                 2027               2028               2029              2030                2031

         BOND SERIES 2030
                   $0.00             $0.00              $0.00             $0.00       $2,760,000.00             $0.00



                   $0.00             $0.00              $0.00             $0.00               $0.00             $0.00



                   $0.00             $0.00              $0.00             $0.00               $0.00             $0.00

         TOTAL:
                   $0.00             $0.00              $0.00             $0.00       $2,760,000.00             $0.00

         PROJECT COST:
         PREVIOUS APPROVED ALLOCATION:                   $0.00

         CAPITAL REMAINING:                       $2,760,000.00
         PROJECT TOTAL                            $2,760,000.00

         PROJECT LOCATION:

         PROJECT LOCATION:              All three (3) locations above
         IMPACT ON OPERATING BUDGET:


         IMPACT ON BUDGET:                               $0.00
         IMPACT:












               FY26 Adopted Budget                           86                                        9/9/25