Wastewater Services - TRA: FY 2025-26 Budget $5,784,103
% of Fund Expenditures 18.0%
Compared to $ Growth % Growth
FY 2024-25 Budget $723,645 14.3%
FY 2024-25 Projection $1,074,103 22.8%
Wastewater treatment is the second largest expense within the Water and Wastewater Fund. The city
holds a contract with TRA for wastewater treatment and collection services. TRA service costs are
anticipated to increase by 10.6%. Increases in this area are charged as a pass-thru and are based upon
TRA’s annual budget requirement.
Debt Service: FY 2025-26 Budget $2,493,002
% of Fund Expenditures 7.7%
Compared to $ Growth % Growth
FY 2024-25 Budget $7,350 0.3%
FY 2024-25 Projection $7,350 0.3%
Debt services relates to the debt obligations made to fund water and wastewater system improvements.
For FY 2025-26, the City does not anticipate issuing new debt.
Transfers: FY 2025-26 Budget $1,927,718
% of Fund Expenditures 6.0%
Compared to $ Growth % Growth
FY 2024-25 Budget $(122,282) (6.0)%
FY 2024-25 Projection $(122,282) (6.0)%
Transfers relate to the annual cash funding of capital projects and are moved into project accounts in
capital improvement project (CIP) funds. For the FY 2025-26 budget, Water and Wastewater CIP includes
$700,000 for maintenance of the Keller Smithfield water tank, $527,718 for utility costs related to street
maintenance, $250,000 for lift station rehabilitation, $200,000 for water line replacements, and $200,000
for future mains and services replacements. For FY 2024-25, the Water and Wastewater CIP included
$400,000 for water line replacements and $200,000 for wastewater line replacements. Also included in
the FY 2024-25 CIP was a one-time transfer of $450,000 for a Material Storage project, $450,000
Pearson Pump repair, $125,000 for Union Church water line relocation, $250,000 for 2023 SWIFT, and
$175,000 for tank maintenance.
Capital Outlay: FY 2025-26 Budget $ 65,000
% of Fund Expenditures 0.2%
Compared to $ Growth % Growth
FY 2024-25 Budget $ - - %
FY 2024-25 Projection $ - - %
The FY 2025-26 Adopted Budget includes capital outlays of $65,000 for laying down asphalt at the MSC.