Wastewater Services - TRA:           FY 2025-26 Budget                   $5,784,103
                                                 % of Fund Expenditures                   18.0%

                                                 Compared to                         $    Growth      % Growth
                                                 FY 2024-25 Budget                     $723,645          14.3%
                                                 FY 2024-25 Projection               $1,074,103          22.8%

            Wastewater treatment is the second largest expense within the Water and Wastewater Fund. The city
            holds a contract with TRA for wastewater treatment and collection services. TRA  service costs are
            anticipated to increase by 10.6%. Increases in this area are charged as a pass-thru and are based upon
            TRA’s annual budget requirement.


            Debt Service:                        FY 2025-26 Budget                   $2,493,002
                                                 % of Fund Expenditures                    7.7%

                                                 Compared to                         $    Growth      % Growth
                                                 FY 2024-25 Budget                       $7,350           0.3%
                                                 FY 2024-25 Projection                   $7,350           0.3%

            Debt services relates to the debt obligations made to fund water and wastewater system improvements.
            For FY 2025-26, the City does not anticipate issuing new debt.


            Transfers:                            FY 2025-26 Budget                   $1,927,718
                                                  % of Fund Expenditures                   6.0%
                                                  Compared to                       $       Growth    % Growth
                                                  FY 2024-25 Budget                   $(122,282)         (6.0)%
                                                  FY 2024-25 Projection               $(122,282)         (6.0)%


            Transfers relate to the annual cash funding of capital projects and are moved into project accounts in
            capital improvement project (CIP) funds. For the FY 2025-26 budget, Water and Wastewater CIP includes
            $700,000 for maintenance of the Keller Smithfield water tank, $527,718 for utility costs related to street
            maintenance, $250,000 for lift station rehabilitation, $200,000 for water line replacements, and $200,000
            for future mains and services replacements. For FY 2024-25, the Water and Wastewater CIP included
            $400,000 for water line replacements and $200,000 for wastewater line replacements. Also included in
            the FY 2024-25 CIP was a one-time transfer of $450,000 for a Material Storage project, $450,000
            Pearson Pump repair, $125,000 for Union Church water line relocation, $250,000 for 2023 SWIFT, and
            $175,000 for tank maintenance.


            Capital Outlay:                       FY 2025-26 Budget                     $ 65,000
                                                  % of Fund Expenditures                   0.2%
                                                  Compared to                        $    Growth      % Growth
                                                  FY 2024-25 Budget                           $ -           - %
                                                  FY 2024-25 Projection                       $ -           - %

            The FY 2025-26 Adopted Budget includes capital outlays of $65,000 for laying down asphalt at the MSC.