CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2024-25  FY 2025-26  FY 2026-27  FY 2027-28  FY 2028-29  FY 2029-30
                                                                                                           YEARS

                                                     STREET SYSTEM


                                               Bear Creek Bridge Erosion Protection

            General Fund               800,000              400,000                                       $       1,200,000
          TOTAL PROJECT   $          800,000   $         400,000   $                      -   $                    -   $                    -   $                     -   $                     -   $       1,200,000
           IMPACT ON O&M  The project provides capital maintenance of an existing bridge and minimal operating impact is anticipated.



                                                   Old Town Keller E. /Bates St.
            General Fund            4,580,000                                                             $       4,580,000
          Street Maintenance
               Fund                                                                                       $                      -
            Debt Issuance                                                                                 $                      -
             KDC Fund                 685,000                                                             $          685,000

            Drainage Fund                                                                                 $                      -
          Water-Wastewater
               Fund                                                                                       $                      -
               Other                                                                                      $                      -
          TOTAL PROJECT   $       5,265,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $       5,265,000
                         The project improves street and related infrastructure on the east side of Old Town Keller and Elm Street. The project includes a pedestrian
                         crossing on 377 and a park on Bates street. The operating impact is related to the estimated annual debt payment.
           IMPACT ON O&M



                                                   Old Town Keller E. /Elm St.

            General Fund                      3,430,000                                                   $       3,430,000
          Street Maintenance                  1,780,000               234,500             351,750         $       2,366,250
               Fund
            Debt Issuance          15,000,000                                                             $     15,000,000

             KDC Fund                                                                                     $                      -
            Drainage Fund                        952,500                                                  $          952,500
          Water-Wastewater                    1,516,730                                                   $       1,516,730
               Fund
               Other                          9,593,270                                                   $       9,593,270
          TOTAL PROJECT   $     15,000,000   $    17,272,500   $          234,500   $        351,750   $                    -   $                     -   $                     -   $     32,858,750
                         The project improves street and related infrastructure on the east side of Old Town Keller and Elm Street. The project includes a pedestrian
                         crossing on 377 and a park on Bates street. The operating impact is related to the estimated annual debt payment.
           IMPACT ON O&M
                                                 $       1,669,296   $     1,668,550   $     1,669,650   $      1,165,875   $      1,165,875
               Other                  635,530                                                             $          635,530
          TOTAL PROJECT   $          635,530   $                     -   $       1,669,296   $     1,668,550   $     1,669,650   $      1,165,875   $      1,165,875   $       7,974,776
           IMPACT ON O&M  The project is improvements of an existing road and minimal operating impact is anticipated.