Page 317 - CityofKellerFY26AdoptedBudget
P. 317
CAPITAL IMPROVEMENT PROJECT BY TYPE SUMMARY
PRIOR YEARS FY 2024-25 FY 2025-26 FY 2026-27 FY 2027-28 FY 2028-29 FY 2029-30 TOTAL ALL YEARS
FACILITIES/GENERAL
GOVERNMENTAL 15,600,000 570,000 - - - - - 16,170,000
POINTE CAPITAL PROJECTS 308,396 - - - - - - 308,396
STREET SYSTEM 54,208,732 24,003,407 5,503,839 3,038,464 4,979,839 20,175,226 3,223,226 115,132,733
PARK SYSTEM 39,834,140 6,876,413 2,170,616 1,300,000 1,725,000 700,000 1,050,000 53,656,169
WATER SYSTEM 27,520,599 104,897 1,450,000 950,000 5,200,000 3,700,000 4,700,000 43,625,496
WASTEWATER SYSTEM 6,628,338 570,103 450,000 450,000 4,200,000 3,700,000 200,000 16,198,441
DRAINAGE UTILITY SYSTEM 2,483,431 340,000 450,000 200,000 150,000 150,000 150,000 3,923,431
Total Project Type $ 146,583,636 $ 32,464,820 $ 10,024,455 $ 5,938,464 $ 16,254,839 $ 28,425,226 $ 9,323,226 $ 249,014,666
Capital Improvement Projects By Type
160,000,000
140,000,000
120,000,000
100,000,000
80,000,000
60,000,000
40,000,000
20,000,000
-
PRIOR YEARS FY 2024-25 FY 2025-26 FY 2026-27 FY 2027-28 FY 2028-29 FY 2029-30
FACILITIES/GENERAL GOVERNMENTAL POINTE CAPITAL PROJECTS STREET SYSTEM
PARK SYSTEM WATER SYSTEM WASTEWATER SYSTEM
DRAINAGE UTILITY SYSTEM
315