                                             Capital Project Request



           Department:    PUBLIC  WORKS                                    Date  Prepared:   March  18, 2022
           Submitted  By:   MAJOR JONES                                    Date Completed:
           Project  Title:   LINE  REPLACEMENT —  DONLEY DRIVE/ DONLEY COURT ENGINEERING
                          WATER
           Project  Type:                               Sub -Type:  MAIN REPLACEMENT
                                                                     B
           Project  Code:                               Priority:
           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR MASTER    PLAN:
           The water mains included in this project are part of the City's Water System Master Plan.














           PROJECT   DESCRIPTION:
           The project consists of the engineering design for the replacement of an existing 6 inch water line located in the
           following areas:

           1.  Along Donley Drive from Glenn Drive to Harwood Road and
           2.  Along Donley Court.






           PROJECT   SCHEDULE:
           FY2027- 28







           JUSTIFICATION:
           Many water mains throughout the City are 50+  years old.  Most of these lines are cast iron or AC and are susceptible
           to deterioration,  leaks,  contamination,  and damage.  This project is part of the systematic replacement of water mains
           using a worst -first approach to reduce maintenance costs and customer problems.