City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27, 2024
Submitted By: MAJOR JONES Date Completed:
Project Title: LINE REPLACEMENT — OAKWOOD TERRACE NORTH PHASE III CONSTRUCTION
WASTEWATER
Project Type: Sub -Type: MAIN REPLACEMENT
B
Project Code: Priority:
RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:
The wastewater mains included in this project are part of the City' s Wastewater System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of wastewater mains in the following areas:
1. Along Eastcliff Drive from Mary Drive to Tyler Avenue and
2. Between Tyler Avenue and Marlene Drive from Eastcliff Drive to Commerce Street.
PROJECT SCHEDULE:
FY2026- 27
JUSTIFICATION:
Many wastewater mains throughout the City are 50+ years old. Most of these lines are clay tile and are susceptible to
ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas. Many are substandard
in size and have inflow/ infiltration problems. This project is part of the systematic replacement of wastewater mains
using a worst -first approach to reduce maintenance costs and customer problems.