PROJECT TITLE:  MISCELLANEOUS     PARK IMPROVEMENTS                        PROJECT CODE:  PR0720

           NET EFFECTS ON OPERATING      AND                    TOTAL ESTIMATED    CAPITAL COST:
           MAINTENANCE    COST (+   OR -)  ANNUAL:

           Direct Operating Cost                                Fixtures,  landscaping,  lighting,

           Personnel:       Full Time                            other park and infrastructure
                            Part Time                         0 improvements
           Total Salary                                       0
           Purchase of Services                                 Minimum  balance $  200, 000)

           Materials &  Supplies
           Utilities






                                                              0
           Subtotal: $                                        0 Total Estimated Capital Cost

           Maintenance  Costs                                   Funding Source:
                                                                Transfer  from:
                                                                EDC Operating Fund                      1, 975, 000
                                                                Developer Contribution ( TRA)             10, 500
                                                              0 ES0283 &  ES1901                          32, 753

           Subtotal: $                                        0 Additional Funding Needed:
          Annual expense $                               97, 566 Transfer from:
                                                                EDC CIP Fund Balance                     100, 000
           Total Estimated Annual Cost $                 97, 566 Total Funding                         2, 118, 253
                                                   CURRENT     STATUS
                                                                               OVER/ UNDER
           PHASE/ FUNDING  SOURCE                      BUDGET      EXPENDED     BUDGET (- +) %        EXPENDED
          Park  Furnishings $                         1, 545, 119 $  1, 241, 836    303, 283               80%
          Landscaping $                                  52, 521 $     42, 021        10, 500              80%
          Contingency $                                  57, 702 $     57, 702             0              100%
          Park Lighting $                               166, 924 $    164, 978         1, 946              99%
          Equipment $                                     3, 170 $      3, 170             0              100%
          Trail/ Sidewalk Improvements $                 55, 795 $     50, 305         5, 490              90%
          Professional Services $                        60, 202 $     31, 680        28, 522              53%
          Improvements $                                129, 067 $    129, 067             0              100%
          Demolition $                                   15, 000 $     14, 970           30               100%
          Improvements ( ES0283- Bear Creek Park) $      27, 753 $          0         27, 753               0%
          Botanical (  ES1901-  Barfield  Foundation) $   5, 000 $          0          5, 000               0%


           TOTAL  PROJECT                             2, 118, 253 $  1, 735, 729 $  382, 524               82%