                                                Capital Project Request



                Department:    COMMUNITY  SERVICES                    Date  Prepared:   April 24,  2018
                Submitted By:   RAY MCDONALD                          Date Completed:

                Project  Title:   TEXAS  STAR  SPORTS  COMPLEX  PHASE  VII
                Project  Type:   PARKS/ RECREATION     Sub -Type:   TSSC IMPROVEMENTS
                Project  CODE:   AC1901                Priority:   A
                COUNCIL  AUTHORIZATION:
                August 14,  2018:  Ratified the Euless Development Corporation ( EDC)  action taken on August 13,  2018,  approving EDC
                Resolution No.  21- 18,  declaring a project for improvements  at the Parks at Texas Star including Softball Facilities.
                October 23,  2018:  Ratified the Euless Development Corporation action taken on October 23, 2018,  authorizing the Euless
                Development  Corporation  President to negotiate and execute an Architectural  Services Contract with Oxley Williams Tharp
                Architects for the planning and design of Texas Star Sports Complex Phase VII ( Softball World).
                November  12,  2019:   Approved  all matters  incident  and  related  to the issuance  and sale  of " Euless  Development  Corporation
                Sales Tax Revenue Bonds,  Series 2019,"  including the adoption of Resolution No.  19- 1559.
                March 24,  2020:  Authorized the purchase and installation of sports turf at the Parks at Texas Star Phase VII from
                GeoSurfaces,  Inc.  through the TIPS Interlocal Purchasing System ( TIPS # 170205)  in the amount of $ 681, 200,  as well as the
                purchase and installation of an LED Retrofit lighting system from GeoSport Lighting Systems,  LLC.  through the TIPS Interlocal
                Purchasing System ( TIPS # 18120601)  in the amount of $ 434, 700.
                April 28,  2020:  Awarded  Bid No.  007- 20 for the purchase and installation  of outfield fence and backstop wall padding for the
                Parks  at Texas  Star  Phase  VII to Sports  Graphics,   Inc.  The estimated  expenditure  is $ 188, 000.
                June 9,  2020:   Awarded  Bid No.  009- 20 for the Parks  at Texas  Star  Phase  VII  renovation  to Henthorn  Commercial
                Construction,  LLC and authorized the City Manager to enter into a contract with Henthorn Commercial  Construction,  LLC.  The
                total  estimated  expenditure  is $ 2, 228, 500.
                August 24,  2020:  Authorized the purchase,  delivery,  and installation of 292, 000 square feet of TifTuf Bermuda sod from Tri-
                Tex Grass,  for the Parks at Texas Star Phase VII through the BuyBoard Cooperative Purchasing Program No.  611- 20.  The
                estimated  expenditure  is $ 137, 240.
                January 24,  2023:  Awarded Bid No.  002- 23 for design/ build services including construction  administration  and general
                contracting services for the Texas Star Athletic Staff Offices and authorized the City Manager to enter into a design/ build
                contract with Gomez Floor Covering,  Inc,  dba GFC Contracting.   The estimated expenditure is $ 411, 914.
                May 28,  2024:  Awarded Bid No.  006- 24 for the construction of the Parks at Texas Star North archway entry sign to Mello
                Signs.  The estimated  expenditure  is $ 148, 232.
                RELATIONSHIP  TO OTHER  PROJECTS  AND/ OR MASTER  PLAN
                The Texas Star Sports Complex Phase VII includes renovating the existing infields with synthetic turf,  renovating the existing
                concession/ restroom building,  building new offices for staff,  and upgrading the existing lighting from metal -halide to LED.  With
                the growing number of participants in youth baseball,  renovating the existing infields with synthetic turf will allow staff the
                opportunity to expand existing leagues as well as programming for additional leagues in adult softball.  Synthetic turf infields
                will also substantially reduce the number of rain outs which results in lost revenue.  The addition of this phase will ensure that
                the Texas Star Sports Complex remains the premier sports facility for amateur athletics for many years to come.


                PROJECT  DESCRIPTION:
                The planning,  design,  and construction for Texas Star Sports Complex Phase VII.  The project scope includes renovating the
                existing infields with synthetic turf,  renovating the existing facility to meet current ADA standards,  renovating the existing
                restroom/ concession building,  creating new office space for staff,  upgrading the lighting system to LED,  new entry signs,  and
                demolition of driveway.

                PROJECT  SCHEDULE:
                Began Design:  January 2019            Office Building Complete:  December 2023
                Design Complete:  May 2020             Archway Entry Sign Construction  Complete:  February 2025
                Began Construction:   July 2020
                Construction  Complete:   April  2021
                JUSTIFICATION:
                With the completion of Phase VII,  the new infields will increase programming  opportunities as well as substantially  reduce the
                number  of rain outs.