Page 264 - CityofEulessFY26AdoptedBudgetOrdinance2432
P. 264

City of Euless

                                            Capital Project Request


                                                                                                   March  31, 2023
           Department:            PUBLIC  WORKS                                Date  Prepared:
           Submitted By:          MAJOR  JONES                                 Date  Completed:
           Project  Title:        LINE  REPLACEMENT —  SOTOGRANDE      BLVD  PHASE I
           Project  Type:         WATER                       Sub - Type:   MAIN  REPLACEMENT

           Project Code:          WT2402                      Priority:   A
           COUNCIL  AUTHORIZATION:













           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR  MASTER   PLAN:
           The water mains included in this project are part of the City' s Water System Master Plan.










           PROJECT   DESCRIPTION:
           The project consists of the replacement of three existing 6 inch AC water line laterals located along Sotogrande
            Boulevard between El Camino Real and Monterrey Boulevard.










           PROJECT SCHEDULE:
            Began Design:  February 2024
            Design Complete:  July 2024
           Anticipate  Begin  Construction:   October  2025
           Anticipate  Construction  Complete:   April  2026





           JUSTIFICATION:
            Many water mains throughout the City are 50+  years old.  Most of these lines are cast iron or AC and are
            susceptible  to deterioration,  leaks,  contamination,  and damage.  This project is part of the systematic
            replacement of water mains using a worst -first approach to reduce maintenance costs and customer problems.









                Ordinance No.  2432,  Page 258 of 474