City of Euless
Capital Project Request
March 31, 2023
Department: PUBLIC WORKS Date Prepared:
Submitted By: MAJOR JONES Date Completed:
Project Title: LINE REPLACEMENT — SOTOGRANDE BLVD PHASE I
Project Type: WATER Sub - Type: MAIN REPLACEMENT
Project Code: WT2402 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:
The water mains included in this project are part of the City' s Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of three existing 6 inch AC water line laterals located along Sotogrande
Boulevard between El Camino Real and Monterrey Boulevard.
PROJECT SCHEDULE:
Began Design: February 2024
Design Complete: July 2024
Anticipate Begin Construction: October 2025
Anticipate Construction Complete: April 2026
JUSTIFICATION:
Many water mains throughout the City are 50+ years old. Most of these lines are cast iron or AC and are
susceptible to deterioration, leaks, contamination, and damage. This project is part of the systematic
replacement of water mains using a worst -first approach to reduce maintenance costs and customer problems.