City of Euless
                                               Capital Project Request



                 Department:   PUBLIC WORKS                           Date Prepared:   May 25,  2018
                 Submitted By:   HAL CRANOR                           Date Completed:

                 Project Title:   FY2018- 19 ST RECON—PIPELINE/ HIGHLAND/ HARWOOD
                 Project Type:   STREET                Sub -Type:   IMPROVEMENTS
                 Project CODE:   PS1902                Priority:   A
                 COUNCIL AUTHORIZATION:
                 December  11,  2018:  Approved  Resolution  No.  18- 1539 authorizing  the City Secretary to publish a notice declaring  intention
                 to issue certificates of obligation.
                 January 22,  2019:  Approved the first and final reading of Ordinance No.  2212,  authorizing issuance of " City of Euless,
                 Texas,  Tax and Waterworks and Sewer System ( Limited Pledge)  Revenue Certificates of Obligation,  Series 2019."
                 December 17,  2019:  Authorized the City Manager to negotiate and execute an Engineering  Design Contract with Halff
                 Associates,  Inc. for the design of the FY2019 Street Reconstruction project.  The estimated expenditure is $ 1, 553, 600.
                 January 12,  2021:  Approved Resolution No. 21- 1597 authorizing the City Secretary to publish a notice declaring intention to
                 issue certificates of obligation.
                 January 12,  2021:  Awarded Bid No.  001- 21 to McMahon Contracting,  LP.  for the FY2019 Street Reconstruction  Phase I
                 project in the amount of $ 10, 078, 330. 84,  authorized an owner -controlled contingency not to exceed 5%,  and authorized the
                 City Manager to enter into a contract with McMahon Contracting,  LP.
                 March 9,  2021:  Approved first and final reading of Ordinance No.  2270 authorizing the issuance of " City of Euless,  Texas,
                 Tax and Waterworks  and  Sewer  System (  Limited  Pledge)   Revenue  Certificates  of Obligation,   Series  2021."
                 March 8,  2022:  Authorized an increase of owner -controlled contingency for the FY2019 Street Reconstruction Phase I
                 project from five percent to six percent of the contractual  amount.
                 February 14,  2023:  Authorized an increase of owner -controlled contingency for the FY2019 Street Reconstruction Phase I
                 project in the amount of $ 27, 133. 62 above the previously approved  six percent.
                 June 25,  2024:  Awarded Bid No.  009- 24 for the FY2019 Street Reconstruction  Phase II,  along West Pipeline Road in the
                 amount of $ 6, 699, 000,  authorized an owner controlled contingency not to exceed 7 percent of the contractual amount
                  468, 930),  and authorized the City Manager to enter into a construction  contract with Reliable Paving,  Inc.
                 October 8,  2024:  Authorized the City Manager to amend the engineering services contract dated January 6,  2020 with Halff
                 Associates,  Inc.  to include construction inspection services on an as needed basis for the duration of Phase II of the FY2019
                 Street  Reconstruction  Project.  The estimated  expenditure  is $ 218, 600.
                 November 26,  2024:  Authorized the City Manager to execute a construction  contract with Fonroche Lighting America for the
                 purchase and installation of solar street lighting along South Pipeline Road.  The estimated expenditure is $ 59, 037.
                 April 8,  2025:  Authorized the City Manager to enter into an Interlocal Agreement with the City of Bedford,  related to roadway
                 improvements  on West  Pipeline  Road.
                 RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:



                 PROJECT  DESCRIPTION:
                 The project scope includes the removal and replacement of asphalt roadway with concrete pavement at the following
                 locations:
                 West Pipeline Road between Arwine Court and Raider Drive;  South Pipeline Road between Royal Parkway and Highland
                 Drive;  Highland Drive;  and Harwood Road between Industrial Boulevard and Main Street.  Each reconstructed street will
                 maintain the same width and lane configuration with the exception of Highland Drive,  which will become a standard 31 foot
                 wide street from back of curb to back of curb;  and South Pipeline Road,  which will become a standard 31 foot wide street.
                 The Highland Drive project will include new sidewalk,  water,  sewer,  and storm drain utilities;  and the South Pipeline Road
                 project will include new sidewalk and a rehabilitated  16"  waterline.
                 PROJECT  SCHEDULE:
                 Phase I -   South Pipeline/ Highland/ Harwood   Phase  II -  West  Pipeline
                 Began Design:  September 2019                   Began Design:  September 2019
                 Design Complete:  November 2020                 Design Complete:  August 2022
                 Began  Construction:   March  2021              Began Construction:   July 2024
                 Construction Complete:  February 2023           Anticipate Construction Complete:  February 2026
                 JUSTIFICATION:
                 The existing asphalt pavement of these streets is deteriorating.  The new concrete streets will increase safety,  reduce
                 maintenance costs,  provide an improved riding surface,  and will enhance the appearance of the streets.