Page 89 - CityofTrophyClubFY25AdoptedBudget
P. 89

Fire Station Apparatus Floor                                              PROJECT #                        0


         PROGRAM: FIRE PROJECT                                PROJECT MANAGER:              JASON WISE



         DESCRIPTION                                             JUSTIFICATION

         Installation of Polycrete and Primer for the            Cracked flooring, discoloration and chipped
         apparatus bay and connected rooms.                      striping.














         FUNDING TIMELINE

         2025                 2026               2027               2028              2029                2030

         MUD FUNDING
                  $0.00             $0.00        $50,000.00              $0.00              $0.00               $0.00



                  $0.00             $0.00              $0.00             $0.00              $0.00               $0.00



                  $0.00             $0.00              $0.00             $0.00              $0.00               $0.00
         TOTAL:

                  $0.00             $0.00        $50,000.00              $0.00              $0.00               $0.00

         PROJECT COST:
         PREVIOUS APPROVED ALLOCATION:                  $0.00

         CAPITAL REMAINING:                        $50,000.00
         PROJECT TOTAL                             $50,000.00

         PROJECT LOCATION:
         PROJECT LOCATIO                    FIRE STATION BAY

         IMPACT ON OPERATING BUDGET:

         IMPACT ON BUDGET:                              $0.00
         IMPACT:












               FY 2024-2025                                  81                    Approved Annual Budget
   84   85   86   87   88   89   90   91   92   93   94