City Of Haltom City Annual Budget, FY2025                   Capital Project Funds










              •  Springdale Road, Ira Street, 3100 Denton Hwy, & Clay Avenue. These residential streets and water
                  and sanitary sewer improvements near 3100 Denton Highway will be grouped into one project.
                  Design is underway and expected to be complete by November 2025 with construction commencing
                  in February 2026 pending available construction funds.
              •  Huddleston  Street.    Design  is  underway  and  expected  to  be  complete  by  October  2025  with
                  construction commencing in December 2025 pending available construction funds.

              •  McComas Road. Project includes the replacement of the sanitary sewer, water main, drainage,
                  sidewalks  and  replacement  of  the  existing  pavement  with  a  concrete  pavement.    Design  is
                  approximately  60%  complete  and  expected  to  be  final  by  Summer  2025  with  construction  to
                  commence end of year 2025.

              •  McCullar  Road.  Project  includes  the  replacement  of  the  sanitary  sewer,  water  main,  drainage,
                  sidewalks and replacement of the pavement with a concrete pavement.  Design is approximately
                  90% complete and expected to be final by Fall 2025 with construction to commence end of year
                  2025.

              •  Denise  Drive.  Project  includes  the  replacement  of  the  sanitary  sewer,  water  main,  drainage,
                  sidewalks and replacement of the pavement with a concrete pavement.  Design is approximately
                  90% complete and expected to be final by Summer 2025 with construction to commence end of
                  year 2025.

              •  Glenview  Drive.  Project  includes  the  replacement  of  the  sanitary  sewer,  water  main,  drainage,
                  sidewalks and replacement of the pavement with a concrete pavement.  The design is expected to
                  be complete by Fall 2025 with construction to commence by the end of 2025.

              •  Broadway  Ave.  Project  includes  the  replacement  of  the  sanitary  sewer,  water  main,  drainage,
                  sidewalks and replacement of the pavement with a concrete pavement.  An engineering agreement
                  is anticipated to be approved by both TxDOT and the City Council in Spring of 2025.  The design is
                  expected to be complete by August 2026 with construction to commence by early 2027.

              •  Eastridge Drive. Project includes the replacement of the sanitary sewer, water main, drainage,
                  sidewalks and replacement of the pavement with a concrete pavement from Broadway Avenue to
                  NE 28th Street.  Engineering firms are being considered for selection.
              •  Midway  Road.  Project  includes  the  replacement  of  the  sanitary  sewer,  water  main,  drainage,
                  sidewalks and replacement of the pavement with a concrete pavement from E. Belknap Street to
                  the eastern city limits.  Engineering firms are being considered for selection.