Storm Drain Condition Assessment - The City is conducting a condition assessment
               of  the  City’s  entire  existing  storm  drain  system.    This  review  will  include  sending  a
               remote  camera  through  the  storm  drain  system  to  digitally  record  its  condition.  The
               scope of work will include surveying each inlet, outlet and storm drain manhole location
               to develop an up-to-date map of the system. The review will assess one quadrant of the
               City’s storm system each year over a four-year period. The project also provides the
               City  with  credits  for  the  Stormwater  Management  Program  and  Community  Rating
               System, that help to reduce flood insurance rates.

               Cedar  Creek  Townhome  Drainage  Project  -  The  Cedar  Creek  Townhomes  are
               located in northeast Benbrook between Bellaire Drive and a natural oxbow of the Trinity
               River.  During heavy rain events, water flows have eroded soil and undermined the
               structural integrity of the  City’s drainage outfall at this location. The project includes
               removal of the existing headwall  and extending the storm drain back in line with the
               bank of the oxbow.  A new headwall will then be constructed at the outfall and the area
               above the extended pipe will be backfilled.

               Timberline Drainage Project - Several local streets that directly connect to Timberline
               Drive significantly flatten out prior to their connection to the collector street.  As a result,
               stormwater ponds on the local streets. The project will extend storm drainpipes from the
               Timberline Drive system to the local streets.  New stormwater curb inlets will be installed
               on the local streets allowing stormwater that would previously pond to flow into the storm
               drain system.

               Low Water Crossing Project – The low water crossing is located on Lake Shore Drive
               behind the Benbrook Stables.  The road must be closed during rain events for safety
               reasons.  The culverts under the low water crossing are deteriorated and need to be
               replaced.  The new culverts will allow water to flow more efficiently under the low water
               crossing thereby reducing the number of times the crossing has to be closed during rain
               events.

               Plantation East Channel Project - Sediment has built up over the years and needs to
               be removed from the channel bottom to allow for better water flow.  The project scope
               includes  the  repair  of  missing  or  damaged  perforated  blocks  that  armor  the  channel
               bottom.