Page 84 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 84

City of Euless
                                               Capital Project Request



                 Department:   PUBLIC WORKS                           Date Prepared:   May 25,  2018
                 Submitted By:   HAL CRANOR                           Date Completed:

                 Project  Title:   FY2019 ST RECON—PIPELINE/ HIGHLAND/ HARWOOD
                 Project Type:   STREET                Sub -Type:   IMPROVEMENTS
                 Project CODE:   PS1902                Priority:   A
                 COUNCIL  AUTHORIZATION:
                 December  11,  2018:  Approved  Resolution  No.  18- 1539 authorizing  the City Secretary to publish a notice declaring  intention
                 to issue certificates of obligation.
                 January 22,  2019:  Approved the first and final reading of Ordinance  No.  2212,  authorizing  issuance  of " City of Euless,
                 Texas,  Tax and Waterworks and Sewer System ( Limited Pledge)  Revenue Certificates of Obligation,  Series 2019".
                 December 17,  2019:  Authorized the City Manager to negotiate and execute an Engineering  Design Contract with Halff
                 Associates,  Inc.  for the design of the FY2019 Street Reconstruction project.  The estimated expenditure is $ 1, 553, 600.
                 January 12,  2021:  Approved Resolution No. 21- 1597 authorizing the City Secretary to publish a notice declaring intention to
                 issue certificates of obligation.
                 January 12,  2021:   Awarded  Bid No.  001- 21 to McMahon  Contracting,  LP.  for the FY2019 Street Reconstruction  Phase I
                 project in the amount of $ 10, 078, 330. 84,  authorized an owner controlled contingency not to exceed 5%,  and authorized the
                 City Manager to enter into a contract with McMahon Contracting,  LP.
                 March 9,  2021:  Approved first and final reading of Ordinance No.  2270 authorizing the issuance of " City of Euless,  Texas,
                 Tax and Waterworks and Sewer System ( Limited Pledge)  Revenue Certificates of Obligation,  Series 2021 ".
                 March 8,  2022:  Authorized an increase of owner -controlled contingency for the FY2019 Street Reconstruction Phase I
                 project from five percent to six percent of the contractual amount.
                 February 14,  2023:  Authorized an increase of owner -controlled contingency for the FY2019 Street Reconstruction  Phase I
                 project in the amount of $ 27, 133. 62 above the previously approved  six percent.

                 RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:








                 PROJECT  DESCRIPTION:
                 The project scope includes the removal and replacement of asphalt roadway with concrete pavement at the following
                 locations:

                 West Pipeline Road between Arwine Court and Raider Drive,  South Pipeline Road between Royal Parkway and Highland
                 Drive,  Highland Drive,  and Harwood Road between Industrial Boulevard and Main Street.  Each reconstructed street will
                 maintain the same width and lane configuration with the exception of Highland Drive,  which will become a standard 31 foot
                 wide street from back of curb to back of curb;  and South Pipeline Road,  which will become a standard 31 foot wide street.
                 The Highland  Drive project will include new sidewalk,  water,  sewer,  and storm drain utilities;  and the South Pipeline Road
                 project will include new sidewalk and a rehabilitated 16"  waterline.



                 PROJECT SCHEDULE:
                 Phase I -   South Pipeline/ Highland/ Harwood   Phase II -  West Pipeline
                 Began Design:  September 2019                   Began Design:  September 2019
                 Design  Complete:   November  2020              Design  Complete:   August  2022
                 Began Construction:  March 2021                 Anticipate Begin Construction:  January 2024
                 Construction  Complete:  February 2023          Anticipate  Construction  Complete:   June  2025
                 JUSTIFICATION:
                 The existing asphalt pavement of these streets is deteriorating.  The new concrete streets will increase safety,  reduce
                 maintenance  costs,  provide an improved  riding surface,  and will enhance the appearance  of the streets.







                Ordinance No.  2360,  Page 84 of 326