Page 78 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 78

City of Euless

                                            Capital Project Request


                                                                                                   March  27, 2014
           Department:            PUBLIC  WORKS                                Date  Prepared:
           Submitted By:          HAL  CRANOR                                  Date  Completed:
           Project  Title:        MISCELLANEOUS    STREET REPAIRS
           Project  Type:         STREET                      Sub - Type:   IMPROVEMENTS

           Project Code:          PS1203                      Priority:   A
           COUNCIL  AUTHORIZATION:
           April 24,  2012:  Authorized  the City Manager to enter into a contract with Estrada Concrete Co.  LLC for concrete
            road repairs at various locations on North Main Street,  Fuller -Wiser Road,  and Bear Creek Parkway in the
            amount of $ 93, 390.
            March 11,  2014:  Authorized the City Manager to negotiate and execute a contract for a citywide pavement
            management  analysis and asset management  inventory with Infrastructure  Management  Services ( IMS).   The
            estimated  expenditure  is $ 82, 155.
            February 26,  2019:  Authorized  the City Manager to execute an Interlocal Agreement  between the City of Euless,
           the City of Bedford,  the City of Colleyville,  and Tarrant County,  Texas for the design and construction  of a traffic
            signal at the intersection  of Heritage Avenue and Cheek- Sparger Road.  Design costs were paid from this project.

















           RELATIONSHIP   TO OTHER PROJECTS AND/ OR MASTER PLAN:
           The Master Thoroughfare Plan identifies the various street types within the City of Euless.  These street types
            include residential streets through regional arterial streets.



           PROJECT   DESCRIPTION:
           This project includes the removal and replacement of deteriorated sections of pavement along identified
            roadways.





           PROJECT   SCHEDULE:






           JUSTIFICATION:
            Continuing repair of the existing street pavement will maintain safe driving conditions and will extend the overall
            life of the City streets.






                Ordinance No.  2360,  Page 78 of 326