City of Euless

                                            Capital Project Request


           Department:            PUBLIC  WORKS                                Date  Prepared:       July 23, 1999
           Submitted By:          RON  YOUNG                                   Date Completed:
           Project  Title:        MISCELLANEOUS    DRAINAGE   IMPROVEMENTS
           Project  Type:         DRAINAGE                    Sub - Type:   IMPROVEMENTS

           Project Code:          DR9903                      Priority:   A
           COUNCIL  AUTHORIZATION:
            May 27,  2014:  Awarded Bid No.  007- 14 to Knight Erosion Control,  Inc. for Drainage Channel Improvements
            along Hurricane Creek and authorized the City Manager to enter into a contract with Knight Erosion Control,  Inc.
           The estimated expenditure is $ 135, 487. 82.
           June 23,  2015:  Ratified City Manager action to proceed with emergency repairs to City property located along
            Hurricane Creek.  The estimated expenditure  is $ 74, 602.
            February 26,  2019:  Authorized the City Manager to execute a construction contract with Knight Erosion Control,
            Inc.  for channel improvements  at the Texas Star Golf Course.  The estimated expenditure  is $ 121, 440.
           January 12,  2021:  Authorized the City Manager to enter into a contract with Knight Erosion Control Retaining
           Walls and Construction,  to proceed with emergency repairs related to the City' s Sanitary Sewer Collection
            System,  finding that the procurement is necessary due to unforeseen damage to an eight inch aerial sanitary
            sewer crossing located along Hurricane Creek near 350 Westpark Way,  and finding that the repair is necessary
           to preserve the public health and protect the safety of the City' s residents.  The estimated expenditure is
             121, 000.
           April 11,  2023:  Awarded Bid No.  011- 23 for channel improvements  at the Texas Star Golf Course to R. C.
            Retaining Walls,  Inc.  The estimated expenditure is $ 130, 751. 36 with an owner -controlled contingency of five
            percent of the contractual amount and will be paid from GC2003 and DR9903.







           RELATIONSHIP   TO OTHER PROJECTS AND/ OR MASTER PLAN:






           PROJECT   DESCRIPTION:
           The project provides funding for various drainage projects or emergency repairs identified throughout the year.
            Often correction of these problems requires design services and other improvements such as bank stabilization.
           As major projects are identified,  they will be tracked separately and assigned a different project number.




           PROJECT   SCHEDULE:






           JUSTIFICATION:
            Failure to correct these problems often causes damage to existing infrastructure.








                Ordinance No.  2360,  Page 70 of 326