Page 302 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 302
City of Euless
Capital Project Request
April 04, 2020
Department: PUBLIC WORKS Date Prepared:
Submitted By: HAL CRANOR Date Completed May 31, 2023
Project Title: LR — MIDWAY PARK 3RD ADDN PH II & GREEN HILLS PRK
Project Type: WASTEWATER Sub - Type: MAIN REPLACEMENT
Project Code: WW2202 Priority: A
COUNCIL AUTHORIZATION:
January 11, 2022: Authorized the City Manager to execute an engineering design contract with Wier &
Associates, Inc. for the design of replacement sanitary sewer mains. The estimated expenditure is $ 63,400.
June 28, 2022: Awarded Bid No. 009- 22 to Douglas Dailey Construction, LLC. for the replacement of sanitary
sewer mains in portions of Midway Park 3rd Addition and Green Hills Park and authorized the City Manager to
enter into a contract with Douglas Dailey Construction, LLC. The estimated expenditure is $ 327,814.
RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Fayette Drive and Ector Drive from Harwood Road to Lamar Drive,
2. Along Donley Drive from a point 1000 feet north of Harwood Road to Harwood Road, and
3. 606, 608, 1304, 1306 and 1308 Glenn Drive.
PROJECT SCHEDULE:
Began Design: January 2022
Design Complete: April 2022
Began Construction: July 2022
Construction Complete: December 2022
JUSTIFICATION:
Many wastewater mains throughout the City are 50+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/ infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst -first approach to reduce maintenance costs and customer
problems.
Ordinance No. 2360, Page 302 of 326