Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 18, 2022
Submitted By: MAJOR JONES Date Completed:
Project Title: LINE REPLACEMENT — DONLEY DRIVE/ DONLEY COURT
WATER
Project Type: Sub -Type: MAIN REPLACEMENT
B
Project Code: Priority:
RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:
The water mains included in this project are part of the City' s Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of an existing 6 inch water line located in the following areas:
1. Donley Drive from Glenn Drive to Harwood Road and
2. Donley Court.
PROJECT SCHEDULE:
FY2028
JUSTIFICATION:
Many water mains throughout the City are 50+ years old. Most of these lines are cast iron and asbestos concrete and
are susceptible to deterioration, leaks, contamination, and damage. This project is part of the systematic replacement
of water mains using a worst -first approach to reduce maintenance costs and customer problems.