Page 106 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 106

City of Euless

                                            Capital Project Request


                                                                                                   March  16, 2022
           Department:            PUBLIC  WORKS                                Date  Prepared:
           Submitted By:          HAL  CRANOR                                  Date  Completed:
           Project  Title:        LINE  REP —  CEDAR HILL ESTATES SOUTH PHASE I
           Project  Type:         WASTEWATER                  Sub - Type:   MAIN  REPLACEMENT

           Project Code:          WW2301                      Priority:   A
           COUNCIL  AUTHORIZATION:
            November 22,  2022:  Authorized  the City Manager to negotiate  and execute an engineering  services contract
           with Plummer Associates,  Inc.  for the design of the FY2023 Sanitary Sewer Rehabilitation  Project.










           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR  MASTER   PLAN:
           The wastewater  mains included  in this project are part of the City' s Wastewater  System Master Plan.










           PROJECT   DESCRIPTION:
           The project consists of the replacement of the following wastewater mains:

            1.   Along Sunset Drive between Vine Street and South Main Street and
            2.  Along Henslee Drive between Whitener Road and Sunset Drive.







           PROJECT SCHEDULE:
            Began  Design:   December  2022
           Anticipate  Design  Complete:   August  2023
           Anticipate Begin Construction:  January 2024
           Anticipate  Construction  Complete:   September  2024





           JUSTIFICATION:
            Many wastewater mains throughout the City are 50+  years old.  Most of these lines are clay tile and are
            susceptible to ground movement,  pulled joints,  root infiltration,  and deterioration from hydrogen sulfide gas.
            Many are substandard in size and have inflow/ infiltration problems.  This project is part of the systematic
            replacement of wastewater mains using a worst -first approach to reduce maintenance costs and customer
            problems.




                Ordinance No.  2360,  Page 106 of 326

                                                             42
   101   102   103   104   105   106   107   108   109   110   111