GOAL 4
Implement the city's Capital Improvement Program to improve the quality of life for
residents through the completion of projects identified in the city’s master plans.
Responsible
Action Target Date
Department
Complete design of Village Creek Second Quarter
2.4.1 Public Works
Parkway (January - March 2024)
Finalize design and complete
construction to improve the condition of Fourth Quarter
2.4.2 Public Works
multiple residential streets throughout the (July - September 2024)
city
Begin construction for bridge connecting Second Quarter
2.4.3 Public Works
Alsbury Boulevard to CR1020 (January - March 2024)
Complete design for Alsbury Boulevard Fourth Quarter
2.4.4 Public Works
extension to Lakewood Drive (July - September 2024)
Complete design of Hulen Street Fourth Quarter
2.4.5 Public Works
expansion from SH174 to Candler Drive (July - September 2024)
Complete design of police station Third Quarter
2.4.6 Public Works
headquarters expansion (April - June 2024)