GOAL 4

    Implement the city's Capital Improvement Program to improve the quality of life for

    residents through the completion of projects identified in the city’s master plans.


                                                                   Responsible
               Action                                                                          Target Date
                                                                   Department




               Complete design of Village Creek                                                Second Quarter
      2.4.1                                                     Public Works
               Parkway                                                                         (January - March 2024)



               Finalize design and complete
               construction to improve the condition of                                        Fourth Quarter
      2.4.2                                                     Public Works
               multiple residential streets throughout the                                     (July - September 2024)
               city



               Begin construction for bridge connecting                                        Second Quarter
      2.4.3                                                     Public Works
               Alsbury Boulevard to CR1020                                                     (January - March 2024)



               Complete design for Alsbury Boulevard                                           Fourth Quarter
      2.4.4                                                     Public Works
               extension to Lakewood Drive                                                     (July - September 2024)



               Complete design of Hulen Street                                                 Fourth Quarter
      2.4.5                                                     Public Works
               expansion from SH174 to Candler Drive                                           (July - September 2024)



               Complete design of police station                                               Third Quarter
      2.4.6                                                     Public Works
               headquarters expansion                                                          (April - June 2024)