Summary of Street Construction and Capital Projects
Note: costs include the expected collection of impact fees and may vary from amounts
borrowed depending upon the anticipated collection of impact fees.
FY 2023 - $17,758,000
• King’s Way, Hillcrest Drive
• Matlock left turn lane at Cannon Drive
• Cardinal Road right turn lane at FM 1187
• Heritage Parkway at S. Main Street intersection
• Heritage Parkway eastbound lanes
• W. Broad Street near Retta Road & Lillian Road
• Seeton Road bridge study
• Walnut Creek Drive bridge at Walnut Creek
• North Street bridge at Walnut Creek
• Summer Trail (Developer Agreement)
• Fort Worth Street, Live Oak Street
• Elizabeth Lane
• Traffic signal at Broad Street/Wisteria
• Debbie Lane median opening at Kroger/Wal-Mart
• Misc. Roadway Improvements
FY 2024 - $19,090,000
• Dick Price Road (design)
• Heritage Parkway/National Parkway reconstruction (design)
• Lone Star Road additional lanes (design)
• U.S. 287 northbound frontage road
• Brown Street, Elm Street
• Mitchell Road asphalt
• Pond Street (design)
• Misc. Roadway Improvements
FY 2025 - $21,820,500
• Dick Price Road (construction)
• Heritage Parkway/National Parkway reconstruction
• Lone Star Road additional lanes (construction)
• U.S. 287 northbound frontage road
• Pond Street (construction)
• Debbie Lane additional lanes (design)
• E. Broad Street reconstruction/addition lanes (design)