Page 374 - FortWorthFY23AdoptedBudget
P. 374

Horizon Issues



            or  PC.    CRM has resulted  in  a higher  number of resident inquiries requiring increased customer service and
            response.  The Program is continuing to monitor how the availability and use of the CRM system impacts the
            number of service requests and service level expectations.

            As the City continues to grow to develop, the Program becomes responsible for more stormwater infrastructure.
            Maintenance  needs  continue  to  be  identified  and  are  outpacing  program  operational  resources,  creating  a
            significant backlog of critical maintenance work.

            Water and Sewer

            SCADA System Replacement: The Utility recently completed an assessment of options to replace the current
            Supervisory Control and Data Acquisition (“SCADA”) system used in its five water treatment plants and Remote
            Terminal Units (“RTUs”) used in 130 remote sites in the distribution system. The current system has been in place
            since 1987 and is reaching the end of its useful life. The project scope will be to replace the SCADA system in the
            water plants and to replace all RTUs in remote sites. The assessment, including an evaluation and alternatives,
            was provided to the Utility in January 2020. Engineering/design has begun with construction expected in Fiscal
            Years 2021 through 2024.

            Revised Lead and Copper Rule: The Environmental Protection Agency issued major changes to this rule, with an
            effective date of December 16, 2021 and a compliance date of October 16, 2024.  A major component of this rule
            is removing and replacing lead service lines.  As of June 2021, the Utility has identified 1,814 lead service lines on
            the City’s side, along with 10 on the customer side.  The City has already replaced 1,473 of these and the remaining
            are scheduled for replacement as part of future water main rehabilitation projects, with a goal of having the
            remaining lines replaced by the end of 2022.  Other requirements of the revised rule include completing a service
            line inventory (88% complete), changes to the sample pool requirement for testing compliance, testing of all
            elementary schools and licensed daycares (a plan for sampling has been initiated), classification of galvanized
            service lines as lead if they were downstream of a lead service line (staff has started documenting), public outreach
            and mandatory public notification and replacement schedules, if there is an action level exceedance.


            Permitting of New Water Reclamation Facility: Wastewater originating from far west Fort Worth currently travels
            more than twenty miles via existing wastewater collection pipes, through the downtown area, before treatment
            at the Village Creek Water Reclamation Facility on the City's east side. As west Fort Worth continues to grow,
            many of these existing pipes will become undersized to handle the proposed wastewater loading. The decision
            was made to invest in the future Mary's Creek WRF that will divert the proposed wastewater flows originating
            from west Fort Worth.  The wastewater will be treated to a high standard and either discharged into Mary's Creek
            or provide a reclaimed water source for developments interested in reuse. Land for the proposed WRF was
            purchased in 2011 and in January 2017, the City Council approved a contract to initiate the permitting process,
            which includes applying for a discharge permit with the Texas Commission on Environmental Quality (TCEQ). The
            Utility filed the permit application with the TCEQ in March 2018. TCEQ deemed the application administratively
            complete in May 2018 and issued a draft permit in FY2020. TCEQ held a public meeting in 2020 and provided a
            response to comments on July 23, 2021.  There were no changes to the draft permit in response to public comment
            and a request for a contested case hearing must be received by TCEQ no later than 30 calendar days from the
            release of their comments. Permit issuance will be followed by design and construction procurement. Under the
            current CIP, the plant could be operational by 2026.


            Cast Iron Pipe: The Utility has prioritized the replacement of cast iron pipe in the water distribution system, as this
            pipe material is responsible for the vast majority of water main breaks each year.  Cast iron pipe makes up less
            than 23% of pipe material in the system, but 83% of breaks in FY2020 and 78% of breaks so far in FY2021 are cast





                                                                                                 Page 374 of 623
   369   370   371   372   373   374   375   376   377   378   379