Page 479 - CityofColleyvilleFY23AdoptedBudget
P. 479

Sidewalks/ Trails
            Sidewalk/trail improvements encompass the installation of new sidewalk/trail segments, removal of obstructions along existing
            segments, and improvements to access ramps to ensure compliance with accessibility standards. Sidewalk/trail improvements
            are targeted to improve pedestrian mobility and access around schools, recreation areas, community centers, and other high
            pedestrian uses.

            Program Summar y: Sidewalks/ Trails

            Parks and Recreation Total    $345,000  $1,050,000  $50,000  $50,000   $0  $1,495,000

            Sidewalks/ Trails              2020     2021     2022     2023     2024     Total

            New Construction
            Annual Sidewalk/Trail
            Construction/Grant Match FY2020  $500,000  —      —        —        —       $500,000
            Bransford Rd Trail (Field St to Cotton   —        —        —        —        $50,000
            Belt Trail)-Design             $50,000
            John McCain Road Trail - Design  $50,000                                     $50,000
            John McCain Road Trail -
            Construction                  $800,000                                      $800,000
            Annual Sidewalk/Trail           —                 —        —        —       $500,000
            Construction/Grant Match FY2021         $500,000
            Bransford Rd Trail (Field St to Cotton  —         —        —        —       $800,000
            Belt Trail)-Construction                $800,000
            Annual Sidewalk/Trail           —        —                 —        —       $500,000
            Construction/Grant Match FY2022                 $500,000
            Annual Sidewalk/Trail           —        —        —                 —       $500,000
            Construction/Grant Match FY2023                          $500,000
            Annual Sidewalk/Trail           —        —        —        —                $500,000
            Construction/Grant Match FY2024                                   $500,000

            New Construction Total       $1,400,000  $1, 300,000  $500,000  $500,000  $500,000  $ 4 , 200,000

            Rehabilitation
            Cheek-Sparger Trail           $400,000   —        —        —        —       $400,000
            Misc Concrete Rehabilitation FY2020  $400,000  —  —        —        —       $400,000


            Sidewalks/ Trails       2023     2024      2025      2026     2027      Total

            New Construction
            Annual Small Segment
            Sidewalk/Trail Construction  $550,000  —    —         —        —        $550,000
            FY2023
            Annual Small Segment
            Sidewalk/Trail Construction  —   $100,000   —         —        —         $100,000
            FY2024
            Annual Small Segment
            Sidewalk/Trail Construction  —    —         $100,000  —        —         $100,000
            FY2025
            Annual Small Segment
            Sidewalk/Trail Construction  —    —         —        $100,000  —         $100,000
            FY2026
            Annual Small Segment
            Sidewalk/Trail Construction  —    —         —         —       $100,000   $100,000
            FY2027
            Bedford Rd Trail (Glade to
            Cheek-Sparger)-           —       —        $1,500,000  —       —       $1,500,000
            Construction




                City of Colleyville | Budget Book 2023                                                    Page 479