STORMWATER CAPITAL PROJECT LIST





 Drainage Project Name  FY 2022  FY 2023  FY 2024  FY 2025  FY 2026  Total Cost


 Erosion Control - Brookhollow Park  $ 0  $ 0  $ 280,600  $ 1,870,688  $ 0  $ 2,151,288

 Rankin Drive   0  0  42,000       278,000                    0         320,000


 Channel Improvements - SH 183 to   400,000  0  1,900,000  0  0      2,300,000

 Bedford Rd

 Tributary Culvert Improvements at   0  330,000  0  2,070,000  0     2,400,000

 Bridges


 Drainage System Study  0  500,000  0       0                 0         500,000

 Total  $ 400,000  $ 830,000  $ 2,222,600  $ 4,218,688      $ 0    $ 7,671,288