Page 206 - CITY OF AZLE, TEXAS
P. 206
City of Azle
Water and Sewer Capital Projects Fund Descriptions
1. Emergency Process Equipment Generator and Onshore Pump Intake Station
This project consists of providing the water treatment plant with an emergency generator with the
ability to produce enough electricity to power all of the primary equipment necessary to safely treat
incoming raw water and all essential monitoring and control equipment. In addition, this project will
add a land-based, raw-water pump station. This will provide an alternative raw-water supply station
that is independent of the current raw-water intake station in Eagle Mountain Lake. Should the
current intake station ever need to be taken out of service for an extended period of time or
experience a long-term failure then the land-based station could continue to supply the water plant
with raw water for treatment and distribution.
Cost: $603,242
Funding Source: Prior Year Bond and C.O. Funds
ARPA Funds
Operating Budget Impact: No direct financial impact on the operating budget is expected as a
result of this project. No additional staff will be required as a third-party
contractor will be hired to perform the construction. Current staff
members will be involved with the project and they must dedicate time
to oversee the project which does take staff time away from routine
duties creating an indirect impact on the operating budget.
Department: Administration
Water Department
2. Meter Endpoint Upgrade
Staff was recently notified by the company that supplies water meters to the City that the 3G cellular
signal the meters utilize to send meter readings to the City will be taken out of service by the various
wireless companies sometime in the next 12 to 24 months. This requires upgrading the meters with
new technology to enable the City to continue to receive meter readings electronically rather than
Staff taking reading from each meter. The supplier will provide the equipment to the City at no
charge but the labor required to complete the upgrade is the responsibility of the City. A contractor
will be hired to perform the necessary labor.
Cost: $170,000
Funding Source: Prior Year Bond and C.O. Funds
2017 SWIFT Fund Bond Issuance Proceeds
Operating Budget Impact: No direct financial impact on the operating budget is expected as a
result of this project. No additional staff will be required as a third-party
contractor will be hired to perform the labor. Current staff members will
be involved with the project and they must dedicate time to oversee the
project which does take staff time away from routine duties creating an
indirect impact on the operating budget.
Department: Administration
Utility Maintenance Department
City of Azle FY 2022-2023 Budget 195