        Public Works                              Preventive Street Maintenance (Multi-Year)             SM1902
                                                      Project Description
        This is for additional funds for the annual program where funds are dedicated to enhance the city's efforts for preventive
        maintenance of city streets. The scope of this project will provide for additional crack sealing, slurry seal and a 2 inch asphalt overlay
        for identified City streets.







                                                      Project Justification
        Preventive maintenance activities delay more costly street reconstruction and extends the life of the current street system.  This
        project provides staff with funding to apply the appropriate maintenance activities to the streets selected for the program.  Depending
        on the current condition of the street and the type of preventive measures taken, the street life can be extended for a minimum cost
        in comparison to a total reconstruction.

        Project Status Update: This project will be utilized as an additional funding source for street maintenance projects through FY 23.












        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2018-19      $1,575,000
        Engineering/Design                                               Total                          $1,575,000
        Land/ROW Acquisition
        Construction                     10/2018         09/2023
        Other
        Total Schedule                   10/2018         09/2023
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation      1,575,000             0                0               0        $1,575,000
        Federal/State Grants
        Reserves
        Sales Tax
        Other
        Total Funding                  $1,575,000            $0               $0              $0        $1,575,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                    1,575,000              0               0               0         $1,575,000
        Other
        Total Costs                    $1,575,000             $0              $0              $0         $1,575,000
        Operating Impact
        Not applicable.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0



                                                                74
                                                                                                     NRH  | TEXAS
   71   72   73   74   75   76   77   78   79   80   81