Page 253 - Project Detail Sheet_AdoptedBook
P. 253

ADOPTED | BUDGET

                                                 Facilities Capital Projects
                Department                                     Project Title                         Project Number
        Facilities and Construction         Concrete Drive Repair at FS #2, FS #5 and Service Center      FC2104
                                                      Project Description
        This request is to replace approximately 6,000 square feet of concrete and subgrade at Firestation #2 ($18,000) and  80' long by 40'
        wide portion of the concrete drive north of Fire Station #5 ($38,400) and replace approximately 60' long by 25' wide portion of
        concrete at the Service Center ($18,000).







                                                      Project Justification
        The concrete drive replacement is due the sub-grade failure from the heavy equipment and trash trucks at these three locations.
        The F&C Department recommends replacement of the concrete, subgrade compaction, drainage improvements, and sealing.  The
        concrete has deteriorated.  Patching the area will only be a temporary solution and continue to deteriorate.
        Note: Project funding source is the Facilities Fund (505).














        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2020-21        $74,400
        Engineering/Design                                               Total                            $74,400
        Land/ROW Acquisition
        Construction                     10/2020         09/2021
        Other
        Total Schedule                   10/2020         09/2021

        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                          74,400              0                0               0          $74,400
        Sales Tax
        Other
        Total Funding                    $74,400             $0               $0              $0           $74,400

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      74,400               0               0               0           $74,400
        Other
        Total Costs                      $74,400              $0              $0              $0           $74,400
        Operating Impact
        None


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0