                                                   Utility Capital Projects
                Department                                     Project Title                         Project Number
        Public Works                             Automatic Control Valve (ACV) Replacement                UT2107
                                                      Project Description
        This project will replace the six automatic control valves (ACV) at Watauga Pump Station. These six valves include: 3 - 10 inch
        valves and 3 - 6 inch valves. The ACV's are a vital component in the process of providing adequate pressure and quantity in the
        water distribution system that serves both the City of North Richland Hills and the City of Watauga. The ACV's main purposes are:
        eliminating pressure spikes, back siphonage, and controlling the flow of water from the pump. The valves are located on the effluent
        side of the six pumps before the discharge header.





                                                      Project Justification
        The Watauga Pump Station provides roughly 814 million gallons of water to the citizens of North Richland Hills and Watauga. Due to
        the age of these valves, repairs have become more frequent to the AVCs and repairs are made by specialized contractors. Parts for
        the valves have become more difficult to find and are causing longer out of service periods. When the valve is out of service, the
        pump that is associated with the valve is also out of service. Without the AVC, the pump will over amp causing a pump failure. Staff
        does not have the training nor the expertise to perform repairs to the ACV.

        Note: Project funding source is the Utility Fund (405).











        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2020-21       $135,000
        Engineering/Design                                               Total                           $135,000
        Land/ROW Acquisition
        Construction                     10/2020         09/2021
        Other
        Total Schedule                   10/2020         09/2021
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                         135,000              0                0               0         $135,000
        Sales Tax
        Other
        Total Funding                   $135,000             $0               $0              $0          $135,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                     135,000               0               0               0          $135,000
        Other
        Total Costs                      $135,000             $0              $0              $0          $135,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0