Major FY 2021-2022 Street Projects
Day Miar Road (Grand Meadow Boulevard to Seeton Road) – $10,820,000
Day Miar Road is planned to be improved to a four-lane undivided concrete roadway. Roadway
drainage will be curb and gutter with inlets and piping draining to an improved parallel open
channel on the west side of the road. The open channel will extend from the south side of Grand
Meadow Blvd. to the detention area north of Lake Ridge High School and then cross to the east
side of the road through an improved culvert. Sidewalks will be included along both sides of the
roadway and traffic signals at the intersections with Grand Meadow Blvd. and Seeton Rd. A
study was completed to analyze the pedestrian needs and safety around the MISD school sites to
determine any additional project safety enhancements. This project will begin when the City of
Grand Prairie nears completion of their reconstruction of Seeton Road. Both cities are
coordinating schedules to assure acceptable traffic routing in this region. City staff is working on
right-of-way acquisition.
North Main Street / FM 157 Connector – $4,450,000
The proposed connector is a four-lane undivided roadway that will provide a connection from
North Main Street to FM 157. This roadway will be located approximately a half mile north of
Mouser Way and will align with the roadway in the future Watson Branch development. The
connector will reduce traffic volume along the frontage of Legacy High School and at the
intersection of Main and FM 157. This project will also eliminate the current skewed
283