Fiscal Year 2022-2026 Capital Improvement Program Total Summary

              Colleyville’s  2022-2026  CIP identifies  projects  ranging from  new infrastructure  and rehabilitation  to
              information technology and equipment.  The program projects are grouped into categories and are funded
              through multiple sources as identified below.


                                           Wastewater  Water  Drainage
                                              2%            0.34%             Information
                                                      6%                      Technology
                                                                                 1%
                                                              Facilities
                                                               17%                   Master
                                                                                   Plans/Studies
                                                                        Parks and      1%
                                                                        Recreation
                                        Streets                           19%
                                         44%




                                                                              Sidewalks/Trails
                                                                                  10%

                                         Fiscal Year 2022-2026 Program Categories


               Project Category       2022           2023           2024         2025        2026         Total


               Drainage               $100,000       $800,000      $300,000     $400,000    $300,000    $1,900,000


               Facilities           $5,015,000      $2,075,000    $1,550,000    $200,000     $50,000    $8,890,000

               Information            $300,000        —              —          $100,000      —          $400,000
               Technology
               Master                 $200,000        —              —            —           —          $200,000
               Plans/Studies

               Parks and            $5,415,000      $5,655,000    $1,300,000    $525,000    $325,000  $13,220,000
               Recreation

               Sidewalks/Trails     $2,850,000      $1,000,000    $2,725,000  $1,850,000  $2,950,000  $11,375,000


               Streets             $12,991,000      $2,922,302    $3,250,000  $1,750,000  $1,000,000  $21,913,302


               Wastewater             $600,000       $300,000        —            —           —          $900,000


               Water                $1,805,539      $2,075,000    $3,550,000  $3,150,000  $4,250,000  $14,830,539


               Total               $29,276,539    $14,827,302    $12,675,000  $7,975,000  $8,875,000  $73,628,841