Page 575 - City of Bedford FY22 Budget
P. 575
SIEDC - Bellvue No 3 Addition (Glenda, Patricia, Hurst)
Re con st r uct ion , r e clam at ion , an d m ill/ov e r lay for v ar ious
st r e e t s.
Su bm i t t ed B y Sta ci Cervi n i , Of {ce Ma n a ger
R equ es t Owner Sta ci Cervi n i , Of {ce Ma n a ger
E s t . St a rt D a t e 1 0 / 0 1 / 20 24
E s t . Com pl et i on D a … 0 9/ 30 / 20 26
D epa rt m ent Streets
T y pe Ca p i ta l Im p rovem en t
Request Details
Proj ec t T y pe Street Im p rovem en t
Capital Cost Capital Cost by Year Capital Cost for All Years
Tot a l Budge t (al l years )
"2.3M
C o ns t r uc t io n (8 5 %) $1, 95 5 , 000. 00
D es ign (15 %) $3 45 , 000. 00
TOTAL $2,300,000.00
C a pit a l C ost Br e a kdown
Ca p ita l Cost FY20 25 FY20 26
D e sig n $ 345,000
Con st r uct ion $ 1,9 55,000
Tota l $34 5, 0 0 0 $1, 955, 0 0 0
City of Bedford, TX | Budget Book 2022 Page 575